PRE-START-UP CHECKLIST
The following data should be checked before putting the unit into operation.
Date:
Place of Work:
Location:
Installing Contractor:
Technician/Company:
Unit Commissioning:
Unit model:
Serial number:
PHYSICAL INSPECTION (BEFORE ELECTRICAL CONNECTION)
Check that the unit has not been damaged by handling or transport.
Visually check for refrigerant leaks.
Open the unit for hydraulic installation only. Do not remove the connection guards until the hydraulic
circuit is closed.
Check for foreign objects in the fan discharge.
Check that the air inlet is not obstructed and has the suggested clearance.
NOTE: Accessories such as thermometers, pressure gauges, measuring ports, etc., are recommended but not necessary for
the operation of the unit. Are recommended but not necessary for the operation of the unit.
INSPECTION OF THE HYDRAULIC CIRCUIT
Date:
Place of Work:
Location:
Installing Contractor:
Technician/Company:
Unit Commissioning:
Unit model:
Serial number:
It is necessary to install a water filter in all hydraulic circuits to prevent the entry of solid particles, these must be installed on the return
side of the circuit and must be cleaned once the initial system load is finished.
iom-cliv-cf-eng
Startup and shutdown procedures
38
www.clima-flex.com