Installation guidelines

3.5 Flange installation requirements

3.4.3

Three channel hybrid cable connection

In a three channel instrument, the electrical wires in the hybrid cables are connected according
to the following figure.
Figure 3-7
Internal power supply
The instrument is designed to feed 3 optics housings using a cable that is not longer than 500m.
3.5
Flange installation requirements
Before the gas analyzer and its optics housings can be used, a pair of process flanges should be
installed at the measurement site. The flanges must be installed at a safe and accessible position
to make installation and service easy to accomplish.
The flanges should be welded to the wall of the furnace or funnel as shown in the figure below.
The flange must protrude at least 100 mm (4") from the wall and 0-30 mm (0-1.2") into the
furnace/funnel.
34
+ – + – + –
Connection of electrical cables for a 3 channel unit
CAUTION
6 pole screw socket for 24 V external power
supply (2 poles per optics housing). Note that
the polarity is not important for non ATEX use
whereas it is for ATEX.