4 COMMISSIONING

4.1 Introduction

Before starting the boiler, the user must be correctly instructed by
the installer, on how to operate the heater, in particular:
− Make sure that the user understands that combustion air
and ventilation openings must not be restricted, closed, or
modified in any way.
− Make sure that the user is informed of all the special mea-
sures to be taken for combustion air inlet and discharg-
ing flue gases, and that these must not be modified in any
way.
− Make sure that the user keeps this manual and all other
documentation included with the boiler.
− Make sure that the user understands never to tamper with
gas control settings and the risk of fire, explosion, or CO
poisoning should an unauthorized individual do so.
− Make sure that the user knows how to adjust temperatures
and controls.
9
WARNING: Do not attempt to dry fire the unit. Starting the unit
without a full water level can seriously damage the unit and
may result in injury to personnel or property damage. This sit-
uation will void any warranty.
9
CAUTION: All of the installation procedures in "Installation"
must be completed before attempting to start the unit.

4.2 Filling the Condensate System

The condensate system must be filled with water according to the
Section 3.10.
9
WARNING: At the Start-up and after prolonged shutdown of
the boiler, the condensate traps and the syphon must be filled
with water prior to restarting it, otherwise combustion gases
will enter the room with a risk of an excessive level of carbon
monoxide.

4.3 Filling the Boiler Heating System

To fill the heating system, proceed as follows:
− Open any automatic air vents in the heating system.
− Open the fill valve and proceed to fill the heating system
and boiler until the pressure gauge (shown on Fig. 40),
reads the pressure for which the heating system is sized.
The heating system water pressure must be higher than 7.5
PSI.
− Check for any water leaking from the fittings. If there is, the
leaks must be repaired.
− Check the pressure gauge during the purging process. If the
pressure has dropped, re-open the fill valve to bring the
pressure back to the desired value.

4.4 Warnings Concerning the Gas Supply

When starting up the unit for the first time the following must be
checked:
− That the unit is supplied with the type of fuel that it is con-
figured to use.
− That the gas supply system is provided with all the safety
devices and controls required under current national and
local codes.
− That the vent and combustion air terminals are properly
connected and free from any blockages.
− That the condensate drain tube is properly connected.

4.4.1 Confirming the Unit's Gas Type

The type of gas and supply pressure for which the unit is config-
ured is listed on the rating label. The Array AR SE Series boilers can
operate using one of the following two gases:
NATURAL GAS
− Maximum supply pressure = 13.5" w.c. (33.6 mbar).
1
Minimum supply pressure = 4" w.c. (10 mbar).
PROPANE (LP) GAS
− Maximum supply pressure = 13.5" w.c. (33.6 mbar).
− Minimum supply pressure = 8" w.c. (19.9 mbar).

4.4.2 Gas Type Conversion

If the gas available at the installation site is not the type the boiler
is configured to use, the boiler must be converted. Special conver-
sion kits are available for this purpose. The gas conversion must be
carried out by a qualified technician.

4.5 Boiler Startup Procedure

To start the boiler, do the following:
− Open the manual gas shut off valve.
− Turn ON the main power switch.
− Push all Module power switches to ON.
− To help remove the air from the hydraulic circuit, the
De-airing function can be started for each module. When
activated, the "De-Air" sequence starts at every power ON
and consists of a controlled cycling of the pumps OFF and
ON that takes 14 minutes, during which no demand will
be served. If the water pressure is too low and the water
pressure switch is in error, the sequence will be suspended
until the pressure switch is ON again. This function can be
started through the Service display, switching the param-
eter (139) Dair_active from No to Yes on each Dependent.
− The Touchscreen Control Panel will switch on. The Splash/
Stand-by screen consists of the R logo:
33