Commissioning and optimization (software)

7.1

Commissioning sequence

The sequence in which the software of a frequency converter in an ET 200 station is
commissioned depends on how complex the drive application is, and on the automation
structure.
The basic drive functions and the higher-level controller are commissioned first and are then
specialized, optimized and the drive application generated.
The parameters and settings that are located during this process can be used for standard
commissioning, if required.
Requirements
A prerequisite for software commissioning is functional hardware that has been
commissioned according to the chapter entitled "Commissioning (hardware)".
A drive configuration has been generated for the converter and the motor has been
commissioned with the factory settings.
Procedure
1. First commissioning and optimization
– Frequency converter/motor combination
– Drive application
– Communication between the S7 CPU and frequency converter
– Fail-safe functions
2. Standard commissioning
Transferring the parameters and settings to other frequency converters