Configuring The Battery And Checking The Power Supply Of The Battery - Huawei UA5000 Commissioning Manual

Universal access unit product
Hide thumbs Also See for UA5000:
Table of Contents

Advertisement

UA5000 Universal Access Unit Product
Commissioning Guide-PVM CLI
Procedure
Step 1 Remove a rectifier unit and check the power supply of the cabinet.
Step 2 Insert the rectifier unit back into the cabinet.
Repeat step 1 and step 2 to verify one by one whether other redundant rectifier units are normal.
----End
Result
After removing any rectifier unit, the power supply and the service of the device board stay
unaffected.
3.4.3 Configuring the Battery and Checking the Power Supply of
the Battery
This topic describes how to configure the battery and verify whether the backup power supplied
by the battery to the AC power system is in the normal state.
Prerequisites
The cabinet must adopt the AC power supply and must be configured with the battery.
Context
l
l
l
Procedure
Step 1 In global config mode, run the emu add command to add the EMU of the power system.
Step 2 In global config mode, run the display emu command to query whether the status of the power
system shows normal.
Step 3 Run the interface emu command to enter the EMU mode to configure the battery parameters.
Issue 04 (2012-06-25)
NOTE
Currently, the encapsulated valve regulated lead acid (VRLA) batteries used in the
communication industry are all produced in full loading state, that is, the battery has been
charged with electricity fully.
Based on the battery features, automatic discharge will occur due to chemical reaction
during the delivery and storage process. In this case, the battery capacity and the open
circuit voltage decrease. We refer to this phenomenon as the automatic charge of the battery.
In a certain period, if you use appropriate methods, the voltage and the capacity of the
battery can be restored completely.
To make up the automatic discharge during the idle period, you need to perform the
supplementary charge for the battery in long idleness periodically. For this type of situation,
refer to "Operation Guide on Battery Supplementary Charge" to complete the
supplementary charge of the battery first, and then perform the following commissioning
procedures.
Huawei Proprietary and Confidential