Order Of Steps For Commissioning The Dp Slave; Start-Up Of The Et 200X - Siemens SIMATIC ET 200X Manual

Distributed i/o device
Table of Contents

Advertisement

Commissioning the DP slave
Table 5-6
Step
1.
2.
Starting up the ET 200X
Supply voltage to the
ET 200X electronics/sensors
The "ON" and "BF" LEDs
ET 200X sets outputs to "0"
and applies set PROFIBUS ad-
dress
ET 200X receives configuration
data from DP master
Does configuration
data agree with real in-
The "BF" LED goes out; inputs
and outputs are enabled;
Data transfer between the
ET 200X and the DP master is
possible.
Figure 5-4
ET 200X Distributed I/O Device
EWA 4NEB 780601602-06

Order of steps for commissioning the DP slave

Turn on the supply voltage to the DP slave.
Turn on the supply voltage to the load as necessary.
come on
No
stallation?
Yes

Start-up of the ET 200X

Commissioning and Diagnostics
Procedure
SF red
BF flashing red
Supply voltage to the
ET 200X electronics/sensors
Match configuration data to
configuration or vice versa