Panasonic EverVolt Mini EVAC-105-2 Installation Manual page 69

5.7/11.4/17.1 kwh ac coupled system
Table of Contents

Advertisement

Maintenance & Cleaning
17. MAINTENANCE & CLEANING
Perform the following maintenance annually or more often if the site
requires it to ensure proper operation.
• Clean the inverter during the cool time of the day, whenever it is visibly
dirty.
• Before cleaning the inverter, make sure to turn off all the breakers (AC,
battery and PV).
• Ensure all connectors on the inverter are clean.
• Periodically inspect the system to ensure all wires and supports are
securely fastened in place.
CAUTION: There are no user-replaceable parts inside the
inverter. Do not attempt to service the unit yourself.
Wiring Diagram
The following diagram shows how the distribution box is electrically
connected to the hybrid inverter. When replacing breakers or wires on the
distribution box the following rules must be observed: (1) All AC breakers
must be sized for 40A or less, and (2) All wiring must be sized for 40A or
more.
NOTES: EverVolt has L1 and L2 connections for two AC input sources,
although it can only accept one source at a time. The inverter has
separate neutral connections for grid input, generator input and output.
These are electrically common. The distribution box is both an input
conduit box and an AC load center. The distribution box also contains
maintenance transfer switches (load selection breaker). Maintenance
transfer switching assemblies allows for the inverter to be taken offline
if necessary without shutting the entire system down. These assemblies
include an interlock mechanism that isolates the AC Lines from each
other.
Installation Manual
69

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Evervolt standard evac-105-4Evervolt plus evac-105-6

Table of Contents