Requirements for installation in Canada

1.
Installations must be made with a vent pipe system certified to ULC-S636.
2.
The first three (3) feet of plastic vent pipe from the appliance flue outlet must be readily accessible for visual
inspection.
3.
The components of the certified vent system must not be interchanged with other vent systems or unlisted
pipe/ fittings. For concentric vent installations, the inner vent tube must be certified vent material in order to
comply with this requirement.
• When utilizing the single pipe method, provisions for combustion and ventilation air must
• The inlet for combustion air can never be located inside a room storing chemicals or
WARNING
• If contaminants are found, you MUST:

Direct venting options

Two pipes wall
See paragraph 9.13 for more details.
Figure 9.6
64
be in accordance with Air for Combustion and Ventilation, of the latest edition of the
National Fuel Gas Code, ANSI Z223.1/NFPA 54, in Canada, the latest edition of CGA
Standard B149 Installation Code for Gas Burning Appliances and Equipment, or
applicable provisions of the local building codes.
contaminants as listed in section 9.8.1. Avoid installing the boiler in any area with
possible contaminants.
• remove contaminants permanently
or
• relocate the boiler and air intake to an area free from all possible contaminants.
E93.1901EN032 Installation and Service Manual SlantFin VGH-CH / CO
Two pipes vertical
See paragraph 9.14 for more details.
Figure 9.7

Advertisement

Table of Contents
loading

Table of Contents