Fitting; General Information On Fitting - Siemens FLENDER H3LV Assembly And Operating Instructions Manual

Gear unit
Table of Contents

Advertisement

6.

Fitting

Observe the instructions in section 3, "Safety instructions"!
6.1

General information on fitting

When transporting the gear unit, observe the notes in section 4, "Transport and storage".
Fitting work must be done with great care by authorised, trained and qualified personnel. The manufacturer
cannot be held liable for damage caused by incorrect assembly and installation.
As early as during the planning phase sufficient free space must be allowed around the gear unit for later
care and maintenance work.
Note
Free convection through the surface of the housing must be ensured by suitable measures.
Adequate lifting equipment must be available before beginning the fitting work.
NOTICE
Material damage
During operation the unit must not be allowed to heat up through exposure to heat from external sources
such as sunlight, and suitable measures must be taken to prevent this.
Heat concentration must be avoided.
This can be done as follows:
– fitting an additional cooling unit
NOTICE
Material damage
Risk of damage to the gear unit caused by falling objects, heaping over, welding work or insufficient
fastening.
The operator must ensure the following:
– The gear unit must be secured against falling objects and heaping over.
– No welding work must be done at all on the drive system.
– The gear unit must not be used as an earthing point for electric­welding operations.
– All the fastening points provided by the design of the unit must be used.
– Screws which have been damaged during assembly or disassembly work must be replaced with new
screws of the same strength class and type.
Note
To ensure proper lubrication during operation, the mounting position specified on the drawings must
always be observed.
BA 5080 en 06/2014
32 / 72

Advertisement

Table of Contents
loading

Table of Contents