Commissioning

36 Commissioning
To ensure correct operation, we recommend that the system is commissioned by our customer service
department.
A commissioning report with checklist is supplied with every appliance and should be worked through before
commissioning.
The key criteria are:
- Has the appliance been positioned and installed in line with the installation and operating instructions?
- Have all electrical and hydraulic connections been completed in full and have you checked that the fan in the
outdoor unit can run freely?
- Are all slides and shut-off valves in the heating water circuit open?
- Have all circuits been flushed and thoroughly vented?
- Is condensate drainage guaranteed?
- Do the power feeds to the compressor, electric heater and control system have omnipolar fuse protection?
- Before commissioning, it is essential to carry out a function test on the circulation pump.