Checking The System Connections - Siemens Siprotec 7VK61 Manual

Breaker management device
Hide thumbs Also See for Siprotec 7VK61:
Table of Contents

Advertisement

Mounting and Commissioning
3.2 Checking Connections
3.2.2

Checking the System Connections

WARNING!
Warning of dangerous voltages
Non-observance of the following measures can result in death, personal injury or substantial property damage.
Therefore, only qualified people who are familiar with and adhere to the safety procedures and precautionary
measures shall perform the inspection steps.
Caution!
Be careful when operating the device on a battery charger without a battery
Non-observance of the following measure can lead to unusually high voltages and consequently, the destruc-
tion of the device.
Do not operate the device on a battery charger without a connected battery. (For limit values see also Technical
Data, Section 4.1).
Before the device is energized for the first time, it should be in the final operating environment for at least 2
hours to equalize the temperature, to minimize humidity and avoid condensation. Connections are checked
with the device at its final location. The plant must first be switched off and earthed.
Proceed as follows in order to check the system connections:
• Protective switches for the power supply and the measured voltages must be switched off.
• Check the continuity of all current and voltage transformer connections against the system and connection
diagrams:
– Are the current transformers earthed properly?
– Are the polarities of the current transformers the same?
– Is the phase relationship of the current transformers correct?
– Are the voltage transformers earthed properly?
– Are the polarities of the voltage transformers correct?
– Is the phase relationship of the voltage transformers correct?
– Is the polarity for current input I
– Is the polarity for voltage input U
• Check the functions of all test switches that are installed for the purposes of secondary testing and isolation
of the device. Of particular importance are test switches in current transformer circuits. Be sure these switch-
es short-circuit the current transformers when they are in the „test mode".
• The short-circuiters of the plug connectors for the current circuits must be checked. This may be performed
with secondary test equipment or other test equipment for checking continuity. Make sure that terminal con-
tinuity is not wrongly simulated in reverse direction via current transformers or their short-circuiters.
– Remove the front cover.
– Remove the ribbon cable connected to the input/output board with the measured current inputs (on the
front side it is the right PCB, for housing size
4 slot 33) and remove the PCB so that there is no more contact with the plug-in terminal.
– At the terminals of the device, check continuity for each pair of terminals that receives current from the
CTs.
210
correct (if used)?
4
correct (if used, e.g. with open delta winding or busbar voltage)?
4
1
/
see Figure 3-3 slot 19, for housing size
3
1
SIPROTEC, 7VK61, Manual
C53000-G1176-C159-3, Release date 05.2009
/
see Figure 3-
2