Installing An Expansion Board In The Secondary Riser Cage - HP ProLiant DL360 Gen10 User Manual

Hide thumbs Also See for ProLiant DL360 Gen10:
Table of Contents

Advertisement

4.
Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
5.
Do one of the following:
a. Extend the server from the rack (Extend the server from the rack on page 24).
b. Remove the server from the rack (Remove the server from the rack on page 25).
6.
Remove the access panel (Remove the access panel on page 25).
7.
Install the secondary low-profile PCIe slot riser cage.
8.
Install one of the following, as needed:
Expansion boards (Installing an expansion board in the secondary riser cage on page 77)
Controllers (Controller options on page 82)
9.
Install the access panel (Installing the access panel on page 25).
10. Install the server into the rack (Installing the server into the rack on page 36).
11. Connect each power cord to the server.
12. Connect each power cord to the power source.
13. Power up the server (Powering up the server on page 24).

Installing an expansion board in the secondary riser cage

Prerequisites
Before installing this option, be sure that you have the following:
The components included with the hardware option kit
Procedure
1.
Observe the following alerts:
WARNING:
To reduce the risk of personal injury from hot surfaces, allow the drives and the internal system
components to cool before touching them.
Installing an expansion board in the secondary riser cage