7.1.2
Recommissioning
Purpose
When recommissioning, the existing configuration on the HMI device is replaced by another.
For this to occur, a new project must be transferred from the configuration computer to the
HMI device.
Instructions for transferring a project from the configuration computer to the HMI device can
be found in the "Transfer" section.
The following options are available for switching the HMI device to transfer mode:
• Start transfer mode manually during the HMI device startup phase.
• When the HMI device is in normal operation, start a manual transfer by pressing the
• Start transfer mode manually with the HMI device in normal operation
7.2
Transfer
7.2.1
Start transfer manually
Procedure
1. Connect the HMI device to the configuration computer using a suitable standard cable.
2. Switch on the power supply to the HMI device.
3. Adapt the interface setting (serial, MPI, USB or Ethernet) in the transfer settings.
4. Close the Control Panel and switch to the transfer mode.
5. Start project transfer on the configuration computer.
TP 270, OP 270, MP 270B (WinCC flexible)
Operating Instructions, Edition 03/2004, 6AV6691-1DD01-0AB0
corresponding operating element in the project.
Use one of the following interfaces depending on the type of transfer:
– IF2 (serial)
– IF1B (MPI/PROFIBUS DP)
– USB
– Ethernet
Transfer via modem is also possible.
Prepare and backup project
7.2 Transfer
7-3