Basic hardware check

This section describes some basic checks that you can do when you start
up the server.

To run the startup test

1
Ensure system is powered down and AC cords are disconnected.
Wait five seconds before turning on the power again.
2
Apply AC power to the server by plugging in the first AC cord and
then the second AC cord. Observe the front panel display.
Figure 3: 1005r front panel.
Result: All the LEDs on the front panel illuminate for a fraction of a
second.
Note: The back panel LEDs on each power supply start blinking
green when the AC power is applied and then turn solid green after