Installation
The determining factor in the depth of the cut into the beam is the thickness of the
drywall. The mounting tabs MUST BE FLUSH against the drywall and therefore, the
depth of the notch depends on that thickness.
4.
Insert one side of the conduit box into the indention on the notched stud and rest the other side of the box
against the opposite beam.
5.
Install and secure a shorter horizontal beam below the conduit box. This beam acts to support the weight
of the box from below and should be secured to both vertical beams (at the sides).
6.
Fasten the CB-TP17 to the Notched stud/beam through the stud fastening holes, located on the inside of
the conduit box (FIG. 35), by using either nails or screws.
7.
Insert a perpendicular block between the Non-Notched stud/beam and the Conduit Box. This block acts
as a bridge to secure the stud/beam to the CB-TP17 along the stud fastening holes located inside of the
box.
8.
Secure the perpendicular block to the Non-Notched stud/beam (FIG. 35) by using either nails or screws.
9.
Fasten the CB-TP17 to the block through the stud fastening holes, located on the inside of the Conduit
Box (FIG. 35), by using either nails or screws.
Drywall/sheetrock
Mounting tabs for
NXD Wall Mount panel
should be flush
with the outside
of the sheetrock
FIG. 35
Screw locations for conduit box attachment in a pre-wall installation
10.
Remove any necessary wiring knockouts from the (optional) conduit box (CB-TP17) (FIG. 35) where the
necessary cables are threaded through for connection to the touch panel.
11.
Thread the incoming RJ-45, Ethernet, and any other audio/video wiring through the knockouts (use of the
top or bottom knockouts are recommended with this installation). Refer to the Wiring Guidelines for the
17" Panels section on page 43 for pinout descriptions. Leave enough slack in the wiring to accommodate
any re-positioning of the panel.
12.
Install the drywall/sheetrock before inserting the main NXD unit into the CB-TP17.
32
Stud
Inserted block bridges the gap
between the Conduit Box and
the notched beam
Knockouts should be located on
the left-side of the conduit box,
alongside the connectors
Stud fastening holes
Conduit Box can be
fastened to both
studs)
Use four #8 flat-head
Mounting Screws to secure
the NXD to the CB
Secure Beam to block
Depth depends on the
thickness of the Drywall
Notched stud