8 8

Vent Clearances and Framing

A. Pipe Clearances to Combustibles
WARNING! Risk of Fire! Maintain air space clearance to
vent. DO NOT pack insulation or other combustibles:
• Between ceiling fi restops
• Between wall shield fi restops
• Around vent system
Failure to keep insulation or other material away from
vent pipe may cause over heating and fi re.
Note: Heat shields MUST overlap by a minimum of 1-1/2 in. (38 mm).
DVP heat shield - designed to be used on a wall 4 in. to 7-1/4 in. (102 mm to 184
mm) thick.
wall thickness is greater than 7-1/4 in. a DVP-HSM-B will be required.
(DVP Pipe Shown)
Heat
3 in. (76 mm)
Shield
top clearance
clearance around
vertical sections
Figure 8.1 Horizontal Venting Clearances To Combustible
Materials
3 in. (76 mm)
top clearance *
Heat
Shield
Wall
clearance
Shield
bottom & sides
Firestop
WALL
Heat & Glo • Everest • 750-900 Rev. W • 10/14
B. Wall Penetration Framing
Combustible Wall Penetration
Whenever a combustible wall is penetrated, you must
frame a hole for the wall shield fi restop(s). The wall shield
fi restop maintains minimum clearances and prevents cold
air infi ltration.
• The opening must be framed on all four sides using the
same size framing materials as those used in the wall
construction.
• DVP pipe - A wall shield fi restop is required on one side
only on interior walls. If your local inspector requires a
wall shield fi restop on both sides, then both wall shield
fi restops must have a heat shield (refer to Section
16.B.) attached to them.
• See Section 10.J. for information for regarding the in-
stallation of a horizontal termination cap.
Non-Combustible Wall Penetration
If the hole being penetrated is surrounded by noncom-
bustible materials such as concrete, a hole with diameter
one inch greater than the pipe is acceptable.
Whenever a non-combustible wall is penetrated, the wall
shield fi restop is only required on one side and no heat
shield is necessary.
Shows center of
10" x 12" vent framing
holes for venting.
D
Framing should be
constructed of 2 X 4
lumber or heavier.
A. ..... 35-1/8" (892 mm)
B. ..... 50-1/2" (1283 mm)
C. ..... 21-3/8" (542 mm)
D. ..... 55-1/2" (1372 mm)
(Center of 12 x 10)
* Shows center of vent framing hole for top or rear venting. The center of the
hole is one (1) in. (25.4 mm) above the center of the horizontal vent pipe.
Figure 8.2 Wall Penetration
C
B
A
29