INSTALL POST IN GROUND

GAS SUPPLY LINE
1. Dig a posthole approximately 12 inches in diameter and 28-3/4 inches in depth at the desired grill
location.
Note: "Normal Installation" height is achieved when the top of the 48 inch post is 24-3/4 inches above
ground. This height provides a cooking surface height of approximately 34 inches above ground.
2. Carefully lower the post into the hole using the following guidelines:
The upper rectangular cut-out is located near the top of the post and should be above ground
after installation.
The rectangular cut-out must face in the same direction as the front of the grill.
Check hole depth and post measurements to ensure desired height.
Note: Make any adjustments at this time.
3. Use concrete pre-mix according to the manufacturer's package directions. Position the post in the
center of the hole. Use a level when aligning the post to achieve precise vertical alignment. Hold the post in
place while pouring the concrete mixture into the hole around the post. Keep concrete below gas line hole.
B102227-4-0615
FLEX LINE
(SUPPLIED BY
EMPIRE)
28-3/4"
ABOVE GRADE
SOIL GRADE
28-3/4" APPROX
DEPTH OF HOLE
CONCRETE OR
STANDARD
PRE-MIX