The boiler can be installed on any suitable internal wall. Provision
must be made to allow the correct routing of the flue and siting of the
terminal to allow the safe and efficient removal of the flue products. A
compartment or cupboard may be used provided that it has been
purpose-built or modified for the purpose. It is not necessary to
provide permanent ventilation for cooling purposes. Detailed
recommendations are given in BS 5440 pt 2. If it is proposed that it is
installed in a timber framed building then reference must be made to
British Gas Document DM2, or advice sought from CORGI.

Flue

Detailed information on flue assembly is contained in the appropriate
starter pack.
The boiler must be installed so that the flue terminal is exposed to
the free passage of external air at all times. It must not be allowed to
discharge into another room or space such as an outhouse or closed
lean-to. The minimum acceptable clearances are shown below:
- A Directly below an opening, window, etc
- B Above an opening, window, etc
- C Horizontally to an opening, window, etc
- D Below gutters, soils pipes or drain pipes
- E Below eaves
- F Below balconies or car port roof
- G From a vertical drain pipe or soil pipe
- H From an internal or external corner
- I Above ground roof or balcony level
- J From a surface facing the terminal
- K From a terminal facing the terminal
- L From an opening in the car port into the dwelling
- M Vertically from a terminal on the same wall
- N Horizontally from a terminal on the same wall
- Q Fixed by Ubbink Rolux 4 GM flue terminal
7

Installing the Boiler

Please check that you are familiar with the installation
requirements before commencing work.(section 6)

Installation

The installation kit includes the flue components and the
flue installation instructions with the boiler you have the
following items :
- Hanging bracket
- A paper template (showing the dimensions of the boiler
with 5 mm side clearances and fitting instructions)
- Connection tails
- Screws and wall plugs
- Connection washers and filters
8
It may be necessary to protect the terminal with a guard. Reference
should be made to the Building Regulations for guidance. Suitable
guards may be obtained from the following manufacturer:

Ventilation

The room in which the boiler is installed does not require specific
ventilation. If it is installed in a cupboard or compartment permanent
ventilation is not required for cooling purposes.

Gas Supply

The gas installation and soundness testing must be in accordance
with the requirements of BS 6891.The boiler requires a 22 mm
supply. Ensure that the pipe size is adequate for demand including
other gas appliances on the same supply.

Electrical Supply

300 mm
The appliance requires an earthed 230V - 50 Hz supply and must
300 mm
be in accordance with current I.E.E. It must also be possible to be
300 mm
able to completely isolate the appliance electrically. Connection
75 mm
should be via a 3 amp fused double-pole isolating switch with
200 mm
contact separation of at least 3 mm on both poles. Alternatively, a
200 mm
fused 3 Amp. 3 pin plug and unswitched socket may be used,
150 mm
provided it is not used in a room containing a bath or shower. It
300 mm
should only supply the appliance.
300 mm
600 mm
1200 mm
1200 mm
1500 mm
300 mm
Q
I
F
B
J
L
A
G
I
Fig. 8

Method of positioning the boiler on the wall.

The paper template can be used to ensure the correct
positioning of kitchen cabinets etc.
The paper template has to be fixed to the wall and used to
locate the position of the hanging bracket, the centre for
the flue hole and, if required, the fixings for the pre-piping
jig.
Drill and plug the wall and secure the hanging bracket
using the screws provided. Remove the boiler from its
packaging as shown in fig. 9 and remove the outer case
as shown in fig.10.
Quinnel Barret & Quinnel Wireworks
Old Kent Road
London SE15 1NL
Tel: 0171 639 1357
Q
D,E
N
C
M
N
H
H
M
Q
K

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents