Hookup To The Existing Heat System (Water To Air); Belt Driven Hot Air Fan; Direct Drive Fan; Thermostat - Pro-Fab Industries Cozeburn Installation And Operation Instructions Manual

Outdoor hot water wood furnace
Table of Contents

Advertisement

Figure 2
Hookup to Existing Heat System
(Water to Air)
1.
Install the circulating pump on the supply line and
ensure that the pump's motor is in a horizontal position.
2.
Install the heat exchange radiator in the hot air plenum
of the forced air furnace, Figure 2, according to the
manufacturer's instructions, taking care to seal all
joints and holes.
3.
After installing the heat exchanger to the forced air
furnace system, check to ensure that the air flow is the
same as specified by the manufacturer of the existing
heating system. The furnace fan should not generally
need to be changed in order to accommodate the
addition of the heat exchanger.

Under Floor Heat

1.
A 24 V thermostat with relay should be used in a
house. For garage or shop, wire pump through an
in-line thermostat.
2.
Each zone can be manually adjusted with the ball
valves on the supply header.
3.
Adjust mixing valve to run supply water temperature
between 110˚F - 120˚F (43˚C -49˚C) in concrete
floor installation.
COZEBURN INSTALLATION AND OPERATION MANUAL

Belt Driven Hot Air Fan

4.
Pulleys on motor and blower
may have to be adjusted to get
the proper rate of air flow.

Direct Drive Fan

5.
Adjust the motor speed to
obtain the correct air flow.

Thermostat

6.
Install a second thermostat to allow the blower to cut in
separately from the furnace.
7.
The existing thermostat should be set several degrees
lower than the new thermostat. This will allow the
regular system to cut in, should the Cozeburn run out
of wood and the temperature drop below the second
setting.
IMPORTANT: Have a qualified electrician check to ensure
that these changes do not cause the electrical motor to be
overloaded. Any modification to the EXISTING forced air
heating system must be made in accordance with the
manufacturer's specifications and performed by qualified,
licensed personnel in accordance with local building codes.
Figure 3
INSTALLATION
Return header