8

Commissioning

.02
Fig. 8 - 08
● Examine the machine, in particular the electric cables and pneumatic connection tubes
for any damage.
● Clean the machine thoroughly and then oil it., see Chapter 10 Care and Maintenance!
● Before commissioning the machine remove plug 1 (Fig. 8 - 08) from its hole and fi ll in oil
up to marking 2, see Chapter 10.03 Oiling the hook.
● Before commissioning the machine remove screw 3 (Fig. 8 - 08a) and fi ll in oil up to the
marking
(inspection glass on the front side of the machine), see Chapter 10.04 Oiling the zigzag
drive.
● Have skilled personnel check if the machine can be operated with the available mains
voltage.
● Connect machine to the compressed air system. The manometer on the air fi lter/
lubricator unit must display a pressure of 6 bar. If necessary, set to the correct value
(see chapter 10.05 Checking / regulating air compression).
1
2
Plug 1 serves as a safety device for transportation and should not be used
during sewing operations.
Do not operate the machine if there is any discrepancy.
The machine may only be connected to an earthed socket!
Have home position of the machine drive verifi ed by certifi ed technicians before
fi rst commissioning! Have settings carried out my technicians where required
(see chapter 8.04)
Installation and commissioning
Fig. 8 - 08a
4
5
3