Connecting the cables
The power cord of connect should be selected according to the following specifications sheet.
Unit
7K
mm2
1.0
1.0
■
Pipe length and the elevation
Capacity
Pipe size
Btu/h
GAS
3/8'' (φ9.52)
9K-12K
1/2'' (φ12.7)
18K-22K
5/8'' (φ15.88)
24K-28K
Caution:Capacity is base on standard length and maximum allowance length is base of reliability.Oil
trap should be install per 5-7 meters.
4、
Indoor unit and outdoor unit explosion diagram and spare parts list(see explosion diagram file)
5. Refrigerant cycle diagram
5.1 Cooling only
Grade
9K
12K
18K
1.5
2.5
Standard length
LIQUID
1/4'' (φ6.35)
1/4'' (φ6.35)
3/8'' (φ9.52)
24K
28K
2.5
2.5
Max.
(m)
Elevation
B (m)
3.5
5
4
10
5
15
9
Max.
Additional
Elevation
refrigerant
A (m)
(g/m)
10
30
15
30
20
65