Step 6

Anchor lift to pad/floor

Anchor the lift to the pad/floor after verifying the running
clearance.
Procedure
1
Ensure the lift is positioned on the pad/floor so there is
an adequate running clearance between the top
landing and the platform per your site plan drawings.
2
Raise the platform to allow you to work underneath.
3
Double-check the position of the lift and then install the
anchor bolts through the four anchor points as shown
below.
4
Before tightening down the bolts, use shims (320651
shown below) as needed to ensure the lift is plumb and
level.
Figure 8
Shim 320651
5
Once complete, lower the platform back down to the
pad/floor.
Figure 9
Anchor points
Part No. 000643, 26-m02-2013
Page 9
Multilift Installation Guide