Step 3

Verify cab type (handing)

Verify the type of cab and the handing.
Procedure
Prior to installation, it is important to know what type of
cab is being installed. The handing is specific to the type of
cab and will determine where the tower is to be installed.
Type 2
Exit (Top)
Exit (Top)
Type 2L
Type 2R
platform
platform
Entrance
Entrance
(Bottom)
(Bottom)
Type 3 and Type 4
Exit
Type 3
platform
Entrance
Multilift Installation Guide
Exit
Type 4
platform
Entrance
Step 4

Position lift

Position the lift.
Procedure
NOTE
The Multilift is shipped fully assembled. Be sure to remove
the shipping straps securing the sling to the tower.
1
Position the lift on the pad/floor ensuring that the
running clearance between the top landing and the
platform is per your plan drawings. Refer to the plan
drawings shipped with your lift. A sample plan drawing
is provided on the next page.
2
Observe the following safety concepts as well.
a. Guarding of top landing
• A door or gate must be used to prevent an
accidental fall from the top landing. This door/gate
must be unlocked ONLY when the lift is level with
the landing.
b. Prevention of shear points along the travel
• A platform moving along stationary objects can
sometimes create crushing and shearing hazards
(see Figure 1 below).
• A typical situation of a shearing hazard is when the
platform crosses the underside of the landing. This
situation can be corrected by the use of a fascia
panel as shown below.
It is critical to recognize possible crushing or shearing
hazards and eliminate them.
Figure 1
Shearing hazard
DANGER
Fascia panel
Part No. 000643, 26-m02-2013