2-1 Installation Procedure

Read the following procedure to familiarize your-
self with the necessary steps before installing the
system.
1.
Create a Layout - Draw a rough sketch of the
building and include all alarm detection devices,
modules and PGM output devices. Refer to the
following paragraphs for wiring requirements.
Keybus,Para 2-3.1
PGMs Para 2-3.2
Hardwired ZonesPara 2-3.3
Telephone Line Wiring.Para 2-3.4
Battery and AC Wiring. Para 2-3.5
Refer to paragraph 2-4 and the associated instal-
lation sheets for placement of wireless detectors.
Locate the control panel in a dry area, near an
unswitched AC source and telephone line. Avoid
areas that are a possible source of electrical noise
such as computers, televisions, appliances,
HVAC systems. Avoid areas with large metal sur-
faces such as heating ducts.
Ensure that the control panel and other
modules will be installed in an area that
will be protected by the system.
Mount Modules - Mount NT9204,
2.
Links2X50, Skyroute modules as indicated in the
associated installation manuals. Mount hard-
wired and PGM output devices as required.
Route Wiring - Route the telephone line, AC
3.
power line, PGM wiring, hardwired zone wiring
or Keybus wiring to the NT9005 panel location.
Install NT9005 Back Cover- Route wiring
4.
through the access holes provided and mount the
back cover. Refer to paragraph 2.2 'NT9005
Installation'.

Chapter 2: Installation

2-1 Installation Procedure
Complete Wiring - Connect the telephone
5.
line, AC power line, PGM wiring, hardwired
zone wiring or Keybus wiring to the back cover.
Power up Control Panel - Connect the
6.
backup battery. Place the unit on mounting plate
ensuring that the header on the printed circuit
board aligns with the terminal block on the back
plate.
The system will NOT power up if only the
battery is connected.
Ensure that the LCD display and buzzer are
functioning as described during the power up
sequence. See Start-up, paragragh 1-5.1.
Position and Enroll Wireless Detectors.
7.
This can be performed in Flash Programming or
section [904] in Advanced Programming (place-
ment only). Refer to the Installation Sheets of
wireless devices to determine optimal placement.
Mount wireless devices after succesful placement.
Refer to appendices C, D and E
8.
Program the System. The system can be
quickly programmed for basic setup in Flash Pro-
gramming or custom programmed manually in
Advanced Programming or with DLS-3 (down-
loading software) using a remote or local com-
puter. See Chap. 3:Programming.
9.
Test the System. Two system tests are avail-
able: the user Walk Test available in [*][6][8]
programming or the installer Walk Test described
in section [901] in Advanced Programming.
In the User Walk Test report codes are not
sent to the central station.