2-1. Starting 24 Gigabit L2 Managed Switch Up

This section will give users a quick start for:

Hardware and Cable Installation

-
- Management Station Installation
- Software booting and configuration
2-1-1. Hardware and Cable Installation
At the beginning, please do first:
Wear a grounding device to avoid the damage from electrostatic discharge
Be sure that power switch is OFF before you insert the power cord to power
source
Installing Optional SFP Fiber Transceivers to the switch
Note: If you have no modules, please skip this section.
Fig. 2-1 Installation of Optional SFP Fiber Transceiver
Connecting the SFP Module to the Chassis:
The optional SFP modules are hot swappable, so you can plug or unplug it
before or after powering on.
1. Verify that the SFP module is the right model and conforms to the chassis
2. Slide the module along the slot. Also be sure that the module is properly
seated against the slot socket/connector
3. Install the media cable for network connection
4. Repeat the above steps, as needed, for each module to be installed into
slot(s)
User Manual
Publication date: January, 2006
Revision A2
9
User Manual
5. Have the power ON after the above procedures are done