Campbell ET107 Instruction Manual
Hide thumbs Also See for ET107:
Table of Contents

Advertisement

Quick Links

ET107 Weather Station
Revision: 5/09
C o p y r i g h t
©
1 9 9 3 - 2 0 0 9
C a m p b e l l
S c i e n t i f i c ,
I n c .

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the ET107 and is the answer not in the manual?

Questions and answers

Summary of Contents for Campbell ET107

  • Page 1 ET107 Weather Station Revision: 5/09 C o p y r i g h t © 1 9 9 3 - 2 0 0 9 C a m p b e l l S c i e n t i f i c ,...
  • Page 2 435-750-9579. Campbell Scientific will not process any returns until we receive this form. If the form is not received within three days of product receipt or is incomplete, the product will be returned to the customer at the customer’s expense.
  • Page 3: Table Of Contents

    ET107 Weather Station Table of Contents PDF viewers note: These page numbers refer to the printed version of this document. Use the Adobe Acrobat® bookmarks tab for links to specific sections. 1. Preparation and Siting ..........1-1 1.1 Siting and Exposure................1-1 1.1.1 Wind Speed and Direction ............
  • Page 4 2.4.9.2 Site Installation ..............2-21 2.4.10 Sensor Connections..............2-22 2.4.11 Sensor Verification and Clock Set .......... 2-24 2.5 Communication Peripherals ..............2-24 2.5.1 Direct Connect to ET107 Station ..........2-24 2.5.2 Phone Modem ................2-26 2.5.2.1 Internal Installation............2-26 2.5.2.2 External Installation............2-27 2.5.3 Short-Haul Modem..............
  • Page 5 1.2-1A. Cut Flap Packing Tape ..............1-3 1.2-1B. Shipping Box Packaging ............... 1-3 1.2-2. ET107 with the Met One 034B-ETM Wind Sensor, Top Layer ..1-4 1.2-3. ET107, Bottom Layer............... 1-4 1.5-1. Magnetic Declination for the Contiguous United States ....1-7 1.5-2.
  • Page 6 2.4-17. Position of Sensor Bulkhead Connectors ........2-22 2.4-18. Connecting Sensor Cabling to Enclosure ........2-23 2.5-1. Close-up of the terminals and 9-pin ports in the ET107 (battery not shown).................. 2-25 2.5-2. Phone Modem Mounting and Connections (battery not shown) ..2-26 2.5-3.
  • Page 7 ET107 Weather Station Table of Contents B.2-2. Both Strut Clamps and Brackets on ET107 Pole ......B-5 B.2-3. Top Clamp Hook Side Up ...............B-6 B.2-4. Enclosure Mounted on ET107 Pole..........B-7 B.2-5. Enclosure Locking Mechanism ............B-8 B.2-6. Mounted Solar Panel................B-9 B.2-7. Procedure for installing and connecting battery ......B-11 Tables 4.1-1.
  • Page 8 ET107 Weather Station Table of Contents This is a blank page.
  • Page 9: Preparation And Siting

    Section 1. Preparation and Siting 1.1 Siting and Exposure CAUTION If any part of the weather station comes in contact with power lines, you could be killed. Contact local utilities for the location of buried utility lines before digging or driving ground rods.
  • Page 10: Solar Radiation

    Section 1. Preparation and Siting 1.1.3 Solar Radiation Pyranometers should be located to avoid shadows on the sensor at any time. Mounting it on the southern most (northern hemisphere) portion of the weather station will minimize the chance of shading from other weather station structures.
  • Page 11: Installation Tasks

    ⇒ Check contents against invoice and shipping checklist. Contact CSI immediately about any shortages. Cut Lower Flap Edge First FIGURE 1.2-1A. Cut Flap Packing Tape Top Packing Foam Layer Middle Packing ET107, Foam Layer Top Layer ET107, Bottom Packing m Layer Foam Layer FIGURE 1.2-1B. Shipping Box Packaging...
  • Page 12: Et107 With The Met One 034B-Etm Wind Sensor, Top Layer

    Wind Set Instruction Instruction Manual Manual Cardboard Cardboard Containing Wind Vane FIGURE 1.2-2. ET107 with the Met One 034B-ETM Wind Sensor, Top Layer Mounting Template Grounding Wire 2-Piece Pole Grounding and AC Transformer and Enclosure Desiccant Packs Lightning Rod and Cabling...
  • Page 13: Outdoors

    Locate suitable site (Section 1) • Prepare concrete base (Section 2) • ET107 Installation: ⇒ Place instrumentation enclosure on the ET pole. Slide enclosure to the top of the pole and secure with correct orientation (Section 2.3). 1.3 Tools Required Tools required to install and maintain a weather station are listed below.
  • Page 14: Supplies For Power And Communications Options

    (Anixter p/n F-02P22BPN (phone 847.677.2600) or equivalent type cable (see Figure 2.1-1). RF450 Antenna for the ET107 station (14205 Yagi antenna recommended). PS24 Power Supply and #18520 Hanger Kit if not using ac power (see Appendix B). 1.5 Determining True North for Wind Vane...
  • Page 15: Nssdc Cgm Service

    Section 1. Preparation and Siting general map showing magnetic declination for the contiguous United States is shown in Figure 1.5-1. Declination angles east of True North are considered negative, and are subtracted from 0 degrees to get True North as shown Figure 1.5-2. Declination angles west of True North are considered positive, and are added to 0 degrees to get True North as shown in Figure 1.5-3.
  • Page 16 Section 1. Preparation and Siting NSSDC Transformation between CGM and GEO coordinates and modeling of the geomagnetic field parameters Results of GEO-CGM calculations: Geocentric IGRF Magnetic Field Oval & Azimuth MLTMN value Lat. Long. Lat. Long. H,Nt D,deg Z,nT angles N/S:+E/W in UT Starting point at...
  • Page 17: Subtracted From 0 To Get True North

    Section 1. Preparation and Siting Magnetic declination is bold in this example to show its location in the table. A positive declination is east, while a negative declination is west. The declination in this example is 13.80 degrees. As shown in Figure 1.5-1, the declination for Logan, UT is east, so True North for this site is 360 –...
  • Page 18 Section 1. Preparation and Siting The State Climatologist, (1985) Publication of the American Association of State Climatologists: Height and Exposure Standards for Sensors on Automated Weather Stations, v. 9, No. 4 October, 1985. EPA, (1989). Quality Assurance Handbook for Air Pollution Measurement Systems, EPA Office of Research and Development, Research Triangle Park, North Carolina 27711.
  • Page 19: Hardware Installation

    CAUTION: Do not fit the 3 meter ET Tower sections together until the appropriate time. Once attached, they cannot be detached. The ET Tower provides a support structure for mounting the ET107 weather station components. Figure 2.1-1 shows a typical ET Tower installation option. The tower is designed to withstand winds of 100 mph.
  • Page 20: Base Foundation

    Section 2. Hardware Installation 2.1 Base Foundation 2.1.1 Supplied Components (3) ½ inch L-Bolts (9) ½ inch Nuts (1) Anchor Template Refer to Section 1 for components supplied by installer and bring components. 2.1.2 Installation 1. The ET Tower attaches to a user supplied concrete foundation constructed as shown in Figure 2.1-2.
  • Page 21: Cement Pad

    Section 2. Hardware Installation SIDE VIEW FORM TOP VIEW 2" FORM WIRE NORTH ANCHOR BOLT 24" 24" SMALL CAVITY CEMENT PAD 24" FORM WIRE TEMPLATE FIGURE 2.1-2. ET Tower Base Installation Conduit Anchor Bolt FIGURE 2.1-3. Cut-Away View Shows Anchor Bolt and Conduit Placement in Cement Pad...
  • Page 22: Ac Power Installation

    Section 2. Hardware Installation 2.1.3 AC Power Installation a) The AC power option includes a 120 VAC to 16 VAC step down transformer. The transformer should be mounted inside a user-supplied junction box according to local electrical codes. Dangerous electrical accidents may be avoided by locating the transformer remotely and burying a low voltage line to the station.
  • Page 23 Section 2. Hardware Installation pole sections is acceptable. Lay the assembled pole on the ground next to the concrete foundation. 3. Cut and save a 9 inch piece of 12 AWG ground wire from the 12 foot length provided. This will be used later to attach the enclosure ground to the lightning rod assembly (reference Figure 2.3-1).
  • Page 24: Tower Grounding

    Section 2. Hardware Installation 4 AWG Wire Ground Rod FIGURE 2.2-2. Close up of Ground Rod and 4 AWG Cable 2.2.3 Tower Grounding 2.2.3.1 Supplied Components (1) 5 foot 4 AWG Ground Cable (1) Copper Ground Lug, Bolt (1) Ground Rod, Clamp 2.2.3.2 Grounding Procedure Ground the tower as shown in Figures 2.2-1 and 2.2-2.
  • Page 25: Enclosure

    Logan, Utah MADE IN USA Ground FIGURE 2.3-1. ET107 Instrumentation Mounted on the ET Tower 2.3.1 Enclosure Installation 1. Mount the ET enclosure on the ET Tower as shown in Figure 2.3-2. Remove the front lid. Remove the connector cover from the back of the ET enclosure by loosening the Phillips screw at the bottom of the cover.
  • Page 26: Crossarm And Sensor Installation

    Adjust the bolts at the base of the pole to vertically level the top section of the mounting pole. Install the ET107 Sensor Arm after the ET Enclosure is mounted on the ET Tower. You may need to temporarily remove the communications option.
  • Page 27: Et107 Sensor Arm Mounting

    Section 2. Hardware Installation Screws FIGURE 2.4-1. ET107 Sensor Arm Mounting 1) Remove the front lid and the protective connector cover from the back of the ET enclosure by loosening the one Phillips screw at the bottom of the cover.
  • Page 28: Rh And Temperature Radiation Shield

    Section 2. Hardware Installation 2.4.3 RH and Temperature Radiation Shield 1. Remove the two Phillips screws taped underneath the crossarm. 2. Remove the yellow shipping cap from off the end of the temperature/relative humidity sensor. See Figures 2.4-2 and 2.4-3. Remove Yellow Cap FIGURE 2.4-2.
  • Page 29: Temperature/Relative Humidity Sensor Without Yellow Protective Cap

    Section 2. Hardware Installation Temp/RH with Cap Removed FIGURE 2.4-3. Temperature/Relative Humidity Sensor without Yellow Protective Cap 3. Insert the temperature/relative humidity into the gill radiation shield until it stops or a “click” is heard. 4. Attach the gill radiation shield to the underside of the crossarm using the two Phillips screws from step 1.
  • Page 30: Wind And Rh/Temperature Sensor Installation

    Section 2. Hardware Installation Temp/% RH Gill Radiation Shield Phillips Mounting Screws FIGURE 2.4-4. Wind and RH/Temperature Sensor Installation Wind Vane Counter Weight Shoulder Screw South UTION ENTIOMETER Alignment ENT 5mA FACE SOUTH Sticker Mounting Alignment Pipe Screw FIGURE 2.4-5. 034B Mounting to Pipe 2-12...
  • Page 31: Gill Windsonic 2-D Ultrasonic Wind Sensor (Wind Sensor Option -Gw)

    Jumper is set at the factory if Gill WindSonic is ordered with the station. When the WindSonic1-ET is added to the ET107, a jumper setting must be changed. The procedure to change the jumper follows: 1. Remove the cover of the enclosure.
  • Page 32: Screws That Secure The Electronics Cover

    Section 2. Hardware Installation Loosen Screws FIGURE 2.4-6. Screws that Secure the Electronics Cover 4. Remove the electronics cover to expose the PCB (see Figure 2.4-7). Lift Here FIGURE 2.4-7. Removal of the Electronics Cover 2-14...
  • Page 33: Attachment To Sensor Arm

    Section 2. Hardware Installation 5. Move the jumper at the top of connector PC board so that it is placed over the center and right pins (see Figure 2.4-8). New Jumper Position FIGURE 2.4-8. Jumper Set for WindSonic1 6. Replace electronics cover. 7.
  • Page 34: Gill Windsonic Mounting Shaft

    Section 2. Hardware Installation FIGURE 2.4-9. Gill WindSonic Mounting Shaft 3. Slide the connector and cable up through the center of the mounting shaft. Plug the cable into the Gill WindSonic sensor. The connector has a key and needs to be pushed in then rotated clockwise to lock it in place. See Figure 2.4-10.
  • Page 35: Rain Gage

    Section 2. Hardware Installation 4. Center the Gill WindSonic over the three threaded screw holes on the mounting shaft and screw it in place using the three Phillips screws taken off the shaft in step 1. 5. Slide the shaft and sensor back through the U-bolt. Align the sensor with north by pointing the small colored dot on outer edge of the bottom of the sensor so it faces true north.
  • Page 36: Pyranometer

    Section 2. Hardware Installation 2.4.7 Pyranometer Level the pyranometer as indicated in Figure 2.4-12. Adjust the three leveling screws until the bubble level indicates plumb. Remove the red or green shipping cap from the pyranometer. See Figure 2.4-13. Leveling Screws FIGURE 2.4-12.
  • Page 37: 107-Lc Or 108-Lc Soil Temperature Sensor (Optional)

    Jumper is set at the factory if CS616-LC is ordered with the station. When the CS616-LC is added to the ET107, a jumper setting must be changed. The procedure to change the jumper follows: 1. Remove the cover of the enclosure.
  • Page 38: Screws That Secure The Electronics Cover

    Section 2. Hardware Installation Loosen Screws FIGURE 2.4-14. Screws that Secure the Electronics Cover 4. Remove the electronics cover to expose the PCB (see Figure 2.4-15). Lift Here FIGURE 2.4-15. Removal of the Electronics Cover 2-20...
  • Page 39: Site Installation

    Section 2. Hardware Installation 5. Move the jumper so that it is placed over the center and right pins (see Figure 2.4-16). New Jumper Position FIGURE 2.4-16. Jumper Set for CS616 6. Replace electronics cover. 7. Tighten screws. 8. Reattach 10588 ribbon cable to the CS I/O port. 9.
  • Page 40: Sensor Connections

    Section 2. Hardware Installation 2.4.10 Sensor Connections Sensor schematics are provided in Section 4.3.1. 1. Each sensor cable plug attaches to a unique bulkhead connector as shown in Figure 2.4-17. The sensor cables are individually marked to match up with the sensor labeling on the back of the enclosure. WARNING The 034B Wind Sensor plugs into the connector labeled WS/WD.
  • Page 41: Connecting Sensor Cabling To Enclosure

    Section 2. Hardware Installation NOTE It’s very important that each plug is completely seated on to the connector and the locking ring turned ¼ revolution clockwise. Failure to seat the plug completely could cause corrosion and water damage to both the enclosure and the sensor cable. Notice how the sensor caps are slid between the connector and NOTE the one above in Figure 2.4-18.
  • Page 42: Sensor Verification And Clock Set

    SDC7 or SDC8: 115,200 Baud 2.5.1 Direct Connect to ET107 Station The ET107 station does not require an interface device for direct RS-232 communication. The inside of the enclosure has a RS-232 and CS I/O port available for communication (see Figure 2.5-1). Most standard communication...
  • Page 43 RJ-11 patch cord radio via the 10588 ribbon cable Connects with Rad Connects with a modem’s 4-wire laptop via an RS-232 patch cable serial cable FIGURE 2.5-1. Close-up of the terminals and 9-pin ports in the ET107 (battery not shown). 2-25...
  • Page 44: Phone Modem

    FIGURE 2.5-2. Phone Modem Mounting and Connections (battery not shown) 2.5.2.1 Internal Installation NOTE If the phone modem was ordered with the ET107, you can skip this section and go directly to the External Installation section. For installation inside the ET Enclosure, the following components are...
  • Page 45: External Installation

    Section 2. Hardware Installation 2. Connect the modem 9-pin port to the ET Enclosure CS I/O port with the P/N 10588 ribbon cable supplied with the ET Enclosure (see Figure 2.5-1 and 2.5-2). 3. Connect the modem RJ-ll jack to the ET Enclosure RJ-11 jack with the RJ-ll patch cord (see Figure 2.5-2).
  • Page 46: Internal Installation

    FIGURE 2.5-3. Short-Haul Modem Mounting and Connection 2.5.3.1 Internal Installation NOTE If the short haul modem was ordered with the ET107, you can skip this section and go directly to the External Installation section. For installation inside the ET Enclosure, the following components are...
  • Page 47: External Installation

    Section 2. Hardware Installation Install the short-haul modems as shown in Figure 2.5-3 and 2.5-4. 1. Mount the Rad / SC932C mounting bracket into the ET Enclosure with the three pre-threaded screws provided. 2. Connect the Rad Modem and SC932C. Strap them into the mounting bracket under the Velcro strap.
  • Page 48: Rf450 900 Mhz, 1 Watt Spread Spectrum Radio

    Section 2. Hardware Installation NOTE The splice and wire nut must be completely immersed into the silicon gel inside the splice tube to be waterproof. 2) Mount the surge protector box to a flat surface within 5 feet of the PC's serial port.
  • Page 49: Power Considerations

    AC power is recommended when using RF450 radios with the station. A 10 watt solar panel can be used but days without sunlight and winter months with little sunlight should be considered. The ET107 station comes with a 7 amp- hour battery that is NOT designed to handle deep discharge. Discharging the battery below 11 Vdc may require battery replacement.
  • Page 50: Internal Installation

    Section 2. Hardware Installation 2.5.4.3 Internal Installation If the RF450 radio was ordered with the ET107, you can skip NOTE this section and go directly to the External Installation section. The following components are provided in the RF450 radio kit for installation...
  • Page 51: External Installation

    Section 2. Hardware Installation 3. Connect the long 9-pin female end of the 10588 ribbon cable to the CS I/O port on the RF450 radio. Screw the connector to the radio using the provided two screws. See Figures 2.5-6. 10588 Ribbon Cable FIGURE 2.5-6.
  • Page 52: Loosely Wire Tie Antenna Cable

    Section 2. Hardware Installation FIGURE 2.5-7. Loosely Wire Tie Antenna Cable FIGURE 2.5-8. Loosely Drape Antenna Cable over Back of Enclosure 2-34...
  • Page 53: Slide Antenna Bracket U-Bolt Around Back Of The Pole

    Section 2. Hardware Installation 3. Use the 2.125 stainless steel U-bolt to attach the adjustable angle mounting bracket to the pole. Depending on the size of the antenna position the bracket directly below, or above, the enclosure top mounting bracket. The top of an omni directional antenna should not be higher than the top of the lightning rod.
  • Page 54: Antenna Bracket Mounted To Pole

    Section 2. Hardware Installation FIGURE 2.5-10. Antenna Bracket Mounted to Pole 4. Mount the saddle bracket to the adjustable angle mount bracket by inserting the ends of the bracket through the quarter circle notches. Put a flat washer, lock washer, and a silicon bronze nut, in that order, on the ends of the saddle bracket.
  • Page 55: Yagi Antenna Mounted To Saddle Bracket

    Section 2. Hardware Installation NOTE Rotate enclosure to expose antenna. Ensure that the solar radiation sensor is not shaded. 5. Use the following procedure to install the Yagi antenna. Mounting hardware that comes in the box with the Yagi antenna NOTE will not be used.
  • Page 56: Wire Tie Antenna Cable To Yagi Antenna

    Section 2. Hardware Installation the BNC connector end of the cable. Take the cover off when you’re done. iv. Use one of the black wire ties to strap the antenna cable to the bundle of sensor cables. v. Tighten up the wire ties holding the antenna cable to the wire tie mount at the top of the enclosure.
  • Page 57: Base Radio Installation

    “RS-232” on the RF450. Plug the wall adapter into a wall outlet and plug the barrel connector into the RF450 connector marked “DC POWER 7- 28V”. You should see the lights on the radio come on. Campbell Scientific Software Settings: • Multi-point master •...
  • Page 58: Base Rf450 Installation

    Section 2. Hardware Installation FIGURE 2.5-15. Base RF450 Installation FIGURE 2.5-16. A Base Radio Installed in an Office 2-40...
  • Page 59: Lightning Rod Installation

    Section 2. Hardware Installation 2.6 Lightning Rod Installation Install lightning rod as shown in Figure 2.6-1 and 2.6-2. 1. Carefully mount the lightning rod clamp to the top of the pole (see Figure 2.6-1). Position the clamp so it won’t interfere with the connector cover. FIGURE 2.6-1.
  • Page 60: Grounding To Lightning Rod Clamp

    Section 2. Hardware Installation FIGURE 2.6-2. Grounding to Lightning Rod Clamp 3. Strip 2.54 cm (1”) from both ends of the 9” (23 cm) piece of 10 AWG green ground wire. Insert one end into the enclosure ground lug located at the top back of the enclosure.
  • Page 61: Solar Panel Installation

    Section 2. Hardware Installation 2.7 Solar Panel Installation FIGURE 2.7-1. Solar Panel Mounting and Cabling a) Mount the solar panel to the tower using the mounting brackets as shown in Figure 2.7-1. Mount the solar panel to the tower so it faces south (northern hemisphere).
  • Page 62: Side View Of Solar Panel Shows Tilt Angle

    Section 2. Hardware Installation Site Latitude Tilt Angle (α) 0 to 10 degrees 10 degrees 11 to 20 Latitude + 5 degrees 21 to 45 Latitude + 10 degrees 46 to 65 Latitude + 15 degrees >65 80 degrees α FIGURE 2.7-2.
  • Page 63: Battery Installation

    The charge light is not effected by the switch. Switching on the power supply without a charging voltage will run the battery down. Figure 2.8-2 shows factory wiring between the PS100 and the enclosure. FIGURE 2.8-2. PS100 to ET107 Enclosure Wiring 2-45...
  • Page 64: Restraining Cables And Sealing/Desiccating Enclosure

    Section 2. Hardware Installation 2.9 Restraining Cables and Sealing/Desiccating Enclosure 2.9.1 Restraining Cables 1. Loosely wire tie power, communication, and grounding cable to the wire tie harness at the top of the back of the station. Do NOT clip back the wire tie at this time.
  • Page 65: Sealing And Desiccating The Enclosure

    Section 2. Hardware Installation FIGURE 2.9-2. Connector Cover in Place 6. Tighten down the wire ties holding cabling to the wire tie harness and clip off any excess. See Figure 2.9-2. 2.9.2 Sealing and Desiccating the Enclosure The ET Enclosure is supplied with two desiccant packs. The desiccant maintains a low humidity in the enclosure to minimize the chance of condensation on the instrumentation.
  • Page 66: Desiccant Installation

    Section 2. Hardware Installation 2) Be sure to close the enclosure hasp securely. A padlock may be used on the latch for extra security. Desiccant FIGURE 2.9-3. Desiccant Installation 2-48...
  • Page 67: Et Software

    A variety of different software packages are available to work with the ET107 station. This section introduces software packages that can be used with the ET107 station. It is not the goal to fully explain capabilities of each package. All software packages mentioned below come with extensive help files.
  • Page 68 Section 3. ET Software This is a blank page.
  • Page 69: Maintenance, Troubleshooting, And Schematics

    Section 4. Maintenance, Troubleshooting, and Schematics 4.1 Maintenance Proper maintenance of the ET107’s components is essential to obtain accurate data. Equipment must be in good operating condition, which requires a program of regular inspection and maintenance. Routine and simple maintenance can be accomplished by the person in charge of the weather station.
  • Page 70: Sensor Maintenance

    Section 4. Maintenance, Troubleshooting, and Schematics Desiccant packs may be ordered in quantity of 20 individually sealed packs at a time (item# 6714) or by the individual pack (item# 4905). Campbell Scientific does have a $50.00 minimum charge. Any orders under $50.00 require a $15.00 handling fee.
  • Page 71: Protective Cap

    To send the sensor to Campbell Scientific for reed switch replacement call for Return Material Authorization number or contact Campbell Scientific for reed switch cost to replace reed switch in the field. • Check calibration of the HMP50-ET temp/RH probe. Sensor will tend to drift up over time giving readings higher then 100%.
  • Page 72: Procedure For Removing Rh Chip

    • Replace 034B-ET’s vane potentiometer if needed (call for part number and price). To send the sensor to Campbell Scientific for potentiometer replacement call for Return Material Authorization number or contact Campbell Scientific for potentiometer cost to replace potentiometer in the field.
  • Page 73: Cr1000M Module

    SRAM when the module is not powered. The CR1000M does not draw power from the lithium battery while it is powered by a 12 VDC supply. In an ET107 stored at room temperature, the lithium battery should last approximately 10 years (less at temperature extremes).
  • Page 74: Troubleshooting

    E. Cycle the power to the datalogger by switching the PS100 power supply to “OFF”, then to “ON” or disconnecting and reconnecting the battery plug. Keypad should power up and the Campbell Scientific logo and text appears on the display.
  • Page 75: Nan Or ±Inf Displayed In A Variable

    Section 4. Maintenance, Troubleshooting, and Schematics E. Check the cable(s) between the serial port and the modem. If cables have not been purchased through Campbell Scientific, check for the following configuration using an ohm meter: 25-pin serial port: computer end...
  • Page 76: Nan Or ±Inf Stored In A Data Table

    Section 4. Maintenance, Troubleshooting, and Schematics 4.2.5 NAN or ±INF Stored in a Data Table A. Something is wrong with the datalogger and/or sensor(s) if Short Cut or VisualWeather was used to create the station program. Make sure the sensor is plugged into the correct bulkhead connector. If CRBasic is used to create the station program verify channel assignments and multipliers.
  • Page 77 Section 4. Maintenance, Troubleshooting, and Schematics TABLE 4.2-1. Multi-Point Network LED Status Master Slave Repeater Condition Carrier Transmit Clear to Carrier Transmit Clear to Carrier Transmit Clear to Detect (TX) Send Detect (TX) Send Detect (TX) Send (CD) (CTS) (CD) (CTS) (CD) (CTS)
  • Page 78: Gill Windsonic1-Et Diagnostic Diagnostic Codes

    Section 4. Maintenance, Troubleshooting, and Schematics Radios not networked together, not communicating: 1. Check the baud rate of all RF450s; they should be the same. 2. Check Network IDs of all RF450s; they should be the same. 3. Check Frequency Key Number of all RF450s; they should be the same unless two branches of the network are operating in a parallel manner.
  • Page 79: Schematics Of Connectors

    Section 4. Maintenance, Troubleshooting, and Schematics TABLE 4.2-2. Gill WindSonic Diagnostic Codes Diagnostic Status Comment Okay All okay Axis 1 Failed Insufficient samples, possible path obstruction Axis 2 Failed Insufficient samples, possible path obstruction Both Axis Failed Insufficient samples, possible path obstruction NVM error Nonvolatile Memory checksum failed ROM error...
  • Page 80: Sensor Schematics

    Section 4. Maintenance, Troubleshooting, and Schematics 4.3.1 Sensor Schematics Schematics of ET107 sensors and associated connectors are provided in Figures 4.3-1 through 4.3-7 for help in troubleshooting. Temp/RH Connector Air Temperature and Relative Humidity Datalogger Sensor Relative Humidity (0-1VDC) Air Temperature (0-1VDC)
  • Page 81: Schematic Of 034B-Lc Wind Speed And Direction Probe And Connector Ws/Wd

    Section 4. Maintenance, Troubleshooting, and Schematics Wind Speed and Wind Direction Sensor Connector 10K OHM Datalogger Excitation Wind Direction WS/WD 1K OHM Signal Return 10K OHM Potentiometer Analog Ground Pulse Wind Speed Magnetically Activated Reed Switch Ground Shield FIGURE 4.3-2. Schematic of 034B-LC Wind Speed and Direction Probe and Connector WS/WD Temp/Sonic Temperature or Gill Connector...
  • Page 82: Schematic Of Cs305-Et Solar Radiation Sensor And Connector Solar Radiation

    Section 4. Maintenance, Troubleshooting, and Schematics Solar Radiation Connector Datalogger Solar Radiation Sensor 450-650 OHMS Not Used Not Used Not Used Shield FIGURE 4.3-4. Schematic of CS305-ET Solar Radiation Sensor and Connector Solar Radiation 4-14...
  • Page 83: Schematic Of Te525-Et Rain Sensor And Connector Rain (Precip)

    Section 4. Maintenance, Troubleshooting, and Schematics Connector Tipping Rain Bucket Rain (Precip) Not Used Not Used Not Used Datalogger Pulse Magnetically Activated Reed Switch Ground Shield FIGURE 4.3-5. Schematic of TE525-ET Rain Sensor and Connector Rain (Precip) 4-15...
  • Page 84: Schematic Of Connector Sdi-12

    Section 4. Maintenance, Troubleshooting, and Schematics Temperature or Soil Volumetric Water Content Connector Datalogger CS616 Signal Return Temperature Signal Return TEMP CS616 Temperature Excitation CS616 +12V Supply +12V CS616 Control Ground FIGURE 4.3-6. Schematic of 107-LC or 108-LC Temperature Probe or CS616-LC Soil Volumetric Water Content Sensor and Connector Temp/CS616 SDI-12 or Temperature Connector...
  • Page 85: Power Schematics

    Section 4. Maintenance, Troubleshooting, and Schematics 4.3.2 Power Schematics 16-19 VAC or 16-24 VDC Solar Panel Power PS100 Charger/Regulator (Solar Panel+) Charge Black Charge (Solar Panel-) Power Note: PS100 Charger/Regulator is not sensitive to polarity. FIGURE 4.3-8. Schematic of Solar Panel and Connector Power 4.3.3 Communication Modems Schematics Short-Haul or Phone Modem Connector...
  • Page 86 Section 4. Maintenance, Troubleshooting, and Schematics 4-18...
  • Page 87: Et107 Maintenance Log

    Appendix A. ET107 Maintenance Log Station Installation Date: __________________ CLEAN/INSPECT RAIN GAGE SENSOR CLEAN/INSPECT RAIN GAGE SENSOR (Recommended - Weekly) (Recommended - Weekly) Date OK/Comments Date OK/Comments...
  • Page 88: Enclosure

    Appendix A. ET107 Maintenance Log REPLACE WIND SPEED BEARINGS AND CLEAN/INSPECT SOLAR RADIATION SENSOR REED SWITCH (Recommended - Monthly) (Recommended - Yearly) Date OK/Comments Date OK/Comments REPLACE RH CHIP (P/N 9598) IN THE HMP50-ET TEMP/% RH SENSOR (Recommended - Yearly)
  • Page 89: Ps24 Components

    Appendix B. PS24 24 Ahr Power Supply and 10 x 12 inch Enclosure The PS24 Power Supply is typically used when the ET107 transmits data via RF450 Spread Spectrum Radios. However, the PS24 can be used for any situation where a larger capacity battery is desirable.
  • Page 90 Appendix B. PS24 24 Ahr Power Supply and 10 x 12 inch Enclosure FIGURE B.1-2. 24 Ahr Battery and Battery Cable...
  • Page 91 Appendix B. PS24 24 Ahr Power Supply and 10 x 12 inch Enclosure HUMIDITY INDICATOR MS20003-2 EXAMINE ITEM FIGURE B.1-3. Enclosure Supply Kit...
  • Page 92: Installation

    Appendix B. PS24 24 Ahr Power Supply and 10 x 12 inch Enclosure B.2 Installation The PS24 is purposely shipped without the battery CAUTION mounted in its bracket. Do not install the battery until instructed to do so. 1. Place the top enclosure bracket on the pole at approximately 40 inches above the bottom of the pole.
  • Page 93 Figure B.2-2 shows the top and bottom brackets correctly positioned on the ET107 pole. FIGURE B.2-2. Both Strut Clamps and Brackets on ET107 Pole...
  • Page 94 Appendix B. PS24 24 Ahr Power Supply and 10 x 12 inch Enclosure 4. Hook the enclosure on the top bracket as shown in Figure B.2-3. FIGURE B.2-3. Top Clamp Hook Side Up...
  • Page 95 5. The bottom enclosure bracket should slide between the top lip of the bottom strut mount bracket and the notch directly below. Move the bottom bracket if necessary, then bolt the bottom bracket down (see Figure B.2-4). CAUTION Do NOT over tighten the bottom bracket. FIGURE B.2-4. Enclosure Mounted on ET107 Pole...
  • Page 96 Appendix B. PS24 24 Ahr Power Supply and 10 x 12 inch Enclosure 6. The bottom enclosure bracket has a small metal locking mechanism. Push up on the small Phillips screw underneath the mechanism and slide it to the left. Once in place, put a small wire tie in the hole to the right of the locking mechanism (see Figure B.2-5).
  • Page 97 8. Throw a blanket or box over the solar panel to prevent any voltage output. 9. Route the solar panel cable and power cable coming from the main ET107 enclosure into the conduit at the bottom of the 10 x 12 enclosure.
  • Page 98 Polarity makes no difference. Connect one wire per CHG NOTE terminal block. 11. Remove the blanket or box from the solar panel once it’s wired in place. 12. Wire the power cable coming from the ET107 station as follows. Power Cable from ET107 to CH100 Red: +12 Black:...
  • Page 99 Appendix B. PS24 24 Ahr Power Supply and 10 x 12 inch Enclosure 13. Follow the Installation of Battery procedure provided in Figure B.2-7. Plug the battery into the connector on the CH100 marked “INT”. FIGURE B.2-7. Procedure for installing and connecting battery 14.
  • Page 100 Appendix B. PS24 24 Ahr Power Supply and 10 x 12 inch Enclosure The enclosure needs to be sealed up tight so don’t be CAUTION stingy with the putty. 17. Put both bags of desiccant inside of the enclosure. 18. Stick the humidity indicator card on a wall inside of the enclosure. Pink on the humidity indicator card means it’s time to CAUTION change the desiccant.
  • Page 101: Exploded Views

    Appendix C. Exploded Views C.1 Enclosure...
  • Page 102 Appendix C. Exploded Views C.2 Crossarm...
  • Page 103: Program For Et107 With Gill Windsonic

    Appendix D. Default Programs D.1 Program for ET107 with Gill WindSonic StationName(ET107_Gill) 'Datalogger status information Public BattVolt Public LogrTmpC Public Encl_RH Public WatchDog Public Overruns Public LowVolts Public LiBattV 'Gill Sonic RS232 variables Public WindSpd_ms Public WindSpd_mph Public WindDir Dim WC_WSmph...
  • Page 104 Appendix D. Default Programs Maximum(1, LogrTmpC, FP2, 0, False) Minimum(1, LogrTmpC, FP2, 0, False) Maximum(1, WindSpd_ms,IEEE4,disable_flag, False) WindVector (1,WindSpd_ms,WindDir,IEEE4,disable_flag,0,0,1) Totalize(1, Rain_mm, FP2, 0) Average(1, AirTempC, FP2, 0) Maximum(1, AirTempC, FP2, 0, False) Minimum(1, AirTempC, FP2, 0, False) Average(1, RelHum, FP2, 0) Maximum(1, RelHum, FP2, 0, False) Minimum(1, RelHum, FP2, 0, False) Average(1, SlrRad_W, FP2, 0)
  • Page 105 Appendix D. Default Programs VoltSe(Encl_RH, 1, mV2500, 10, False, 0, _60Hz, 0.1, 0) If Encl_RH > 100 Then Encl_RH = 100 SerialInRecord (Com1,in_bytes_str,&h02,0,&h0d0a,nmbr_bytes_rtrnd,01) WindDir = Mid (in_bytes_str,3,3) WindSpd_ms = Mid (in_bytes_str,7,6) diag = Mid (in_bytes_str,16,2) checksum_flg = ( (HexToDec (Mid (in_bytes_str,20,2))) EQV (CheckSum (in_bytes_str,9,18))) disable_flag = (NOT (checksum_flg) OR (nmbr_bytes_rtrnd=0) OR (diag<>0)) WindSpd_mph = WindSpd_ms * 2.236936 PulseCount(Rain_mm, 1, 2, 2, 0, 0.254, 0)
  • Page 106: Program For Et107 With 034B

    Appendix D. Default Programs HeatIndxC = (5/9) * (HeatIndxC - 32) CallTable VW_Hourly CallTable STATS NextScan EndProg D.2 Program for ET107 with 034B StationName(ET107_034B) 'Datalogger status information Public BattVolt Public LogrTmpC Public Encl_RH Public WatchDog Public Overruns Public LowVolts Public LiBattV...
  • Page 107 Appendix D. Default Programs WindVector (1,WindSpd_ms,WindDir,FP2,False,0,0,1) FieldNames ("WindSpd_ms_Avg,WindDir_Avg") Totalize(1, Rain_mm, FP2, 0) Average(1, AirTempC, FP2, 0) Maximum(1, AirTempC, FP2, 0, False) Minimum(1, AirTempC, FP2, 0, False) Average(1, RelHum, FP2, 0) Maximum(1, RelHum, FP2, 0, False) Minimum(1, RelHum, FP2, 0, False) Average(1, SlrRad_W, FP2, 0) Maximum(1, SlrRad_W, FP2, 0, False) Maximum (1,DewPntC,FP2,False,False)
  • Page 108 Appendix D. Default Programs VoltSe(RelHum, 1, mV2500, 1, False, 0, _60Hz, 0.1, 0) If (RelHum >= 100) AND (RelHum < 108) Then RelHum = 100 AirTempF = AirTempC * 1.8 + 32 VoltDiff(SlrRad_W, 1, mV7_5, 3, true, 0, _60Hz, 200, 0) If (SlrRad_W <...
  • Page 110 Campbell Scientific Companies Campbell Scientific, Inc. (CSI) 815 West 1800 North Logan, Utah 84321 UNITED STATES www.campbellsci.com • info@campbellsci.com Campbell Scientific Africa Pty. Ltd. (CSAf) PO Box 2450 Somerset West 7129 SOUTH AFRICA www.csafrica.co.za • cleroux@csafrica.co.za Campbell Scientific Australia Pty. Ltd. (CSA)

Table of Contents