Precaution

This equipment is intended for indoor use only. Do not use it
outdoors or at places that are exposed to rain or moisture.
Do not attach devices other than TK-C625U/E, TK-C655E, TK-
C676E, TK-C205(A)U/E, TK-C205VP(A)U/E, VN-C625U and
VN-C655U to this mount/bracket.
Install this mount/bracket horizontally. Do not tilt it during use.
Do not install or use the unit in the following places.
• In a place exposed to rain or moisture.
• In a temperature outsside the operating temperature range
(–10˚C to 50˚C (14˚F to 122˚F)).
• In a place where corrosive gasses are generated.
• In a place subject to vibration.
When attaching VN-C625U, VN-C655U to this mount/bracket,
please refer to the "INSTRUCTIONS" section of VN-C625U, VN-
C655U for procedures to install the converter unit.
Please refer to the "INSTRUCTIONS" section of the camera in
use for procedures to attach the camera.

Installation Procedures

WB-S621U Pendant Mount

When a hole is not
made in the ceiling
Groove
Cable
4.
Fall prevention
Safety cable Mount
Hole ( 4.5 mm)
Bolt (M4)
Nut (M4)
Rear Mark
Camera
Mounting Plate
Ceiling Panel Assy
(for attaching
TK-C625U/E
and VN-C625U)
Reinforcement Angle
2.
Safety cable
1.
Cables
3.
FRONT Mark
Ceiling Panel
A s s e m b l y
Positioning
Hole
Screws
(3 locations)
5.
Protruding Part

Installing the Converter Unit

When using VN-C625U or VN-C655U, attach using the clamping bracket
inside the top cover of the converter unit (supplied with the camera).
1.
Make a hole in the ceiling.
To route cables through the ceiling, make a hole of
in the ceiling.
2.
Route the safety cable and other cables
Route the safety cable and cables that is attached to the reinforce-
ment angle through the pendant mount.
When a hole is not made in the ceiling, route the cables through the
groove of the pendant Mount.
3.
Mount the Pendant Mount to the Ceiling.
Attach the pendant mount to the ceiling using 4 or bolts (M5 - M6).
CAUTION
The camera may drop or images on the screen may appear shaky
if the ceiling material is not strong enough. In this case, reinforce
using a reinforcement materials.
4.
Connect the safety cable.
Upon removing the camera mounting plate, attach the safety cable
(not supplied) to the safety cable mount hole ( 4.5 mm ( 1/8")) at
the interior of the top cover using the M4 Bolt (not supplied) and M4
Nut (not supplied).
When attaching the camera mounting plate, ensure that the Front
mark on the camera mounting plate is facing a direction opposite to
the Rear mark on the top cover.
CAUTION
Pay particular caution to the length, strength, pull and material of
the safety cable in use to prevent the plate from falling.
5.
Install the ceiling panel assembly (for attach-
ing TK-C625U/E and VN-C625U)
To install, align the protruding part of the ceiling panel assembly
with the ceiling panel assembly positioning hole near the Front mark
of the camera mounting plate. Ensure to tighten the screws (3
locations) assembled to the ceiling panel assembly.
NOTE
The screws are assembled to the ceiling panel assembly in such
a way that they will not come off.
Top cover
6.

Connect the Cables.

Connect cables to the camera.
For details, please refer to "INSTRUCTIONS" section of the camera
in use.
7.
Attach the camera's ceiling mount. (Not applicable
to TK-C205(A)U/E and TK-C205VP(A)U/E)
Attach the camera's ceiling mount to the camera mounting plate
using the 4 screws (M4 x 20 mm) supplied with the pendant mount.
Ensure that the FRONT mark on the camera mounting plate aligns
with the Front mark on the ceiling mount.
Converter Unit
Top cover
Clamping Bracket
30 mm ( 1 1/4)
Table of Contents
loading
Need help?

Need help?

Do you have a question about the Ceiling Bracket WB-S623U and is the answer not in the manual?

This manual is also suitable for:

Wb-s622uWb-s621u

Table of Contents