2. Verify the Switch Passes Self Test
Before mounting the switch in its network location, you should first verify it
is working properly by plugging it into a power source and verifying it passes
its self test.
1.
For the HP 2530 24-port and 48-port switches, connect the power cord
supplied with the switch to the power connector on the back of the switch,
and then into a properly grounded electrical outlet.
For the HP 2530 8-port switches, connect the AC/DC adapter's power cord
to the power connector on the back of the switch, and then plug the AC/
DC power adapter into a nearby properly grounded electrical outlet.
Figure 2-1. Connecting the power cord
Installing the Switch
Installation Procedures
HP 2530 24-Port and
48-Port Switches
Connect power cord to the
power connector
HP 2530 8-Port Switches
Connect inline AC/DC power adapter
to the switch and an AC power outlet
2-7