Site Location And Preparation; Site Location; Gas Supply - Hamworthy F175H Installation, Commissioning And Operating Instructions

Fleet series floor standing, condensing , room sealed, fully modulating, pre-mix, gas fired boilers for heating & domestic hot water installations
Table of Contents

Advertisement

4.0 SITE LOCATION AND PREPARATION

4.1 Site Location.

The boiler is heavy. Care must be taken when lifting the boiler
The floor or plinth for the boilers and pipe work kit must be both flat and level to ensure
correct alignment of fittings and connections.
The floor or plinth must be sufficiently strong to support the weight of both the boilers
and pipe work kit where used.
The floor or plinth must be fireproof in accordance with BS 6644.
The plant room must have sufficient space for installation of boilers, pipe work, pumps
controls, flues ventilation, access and servicing and other items of plant.

4.2 Gas Supply.

Gas supply pipes must be in accordance with BS 6891 or IGE/UP/2
Gas supply connections to the boiler must not be smaller than the connection on the
boiler - refer to Figure 4.2 & Appendix 2 for the connection size.
Gas installation must be soundness tested to BS 6891 or IGE/UP/1 & IGE/UP/1A.
Gas installation must be purged to BS 6891 or IGE/UP/1 & IGE/UP/1A.
Inlet gas pressure to boiler measured at the gas valve, nominal 20mbar (minimum
17.5mbar) dynamic - refer to Appendix A
Boiler house gas isolation valve must be clearly identified and installed close to the
entrance / exit.
Gas connection
Figure 4.2 - Gas Connection Point
HAMWORTHY HEATING LTD
9
FLEET H series
500001216/D

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

F200hF350hF250hF300h

Table of Contents