12"
(305mm)
Max. Length
Fig. 25 Assemble the wall sleeve and firestop.
ZCS103
For DuraVent pipe only: Install vent pipe by align-
Zero Clearance Sleeve
ing the locking system together, sliding the pipes
& Firestop
together and twisting clockwise.
12/6/99 djt
Install 90° elbow. Twist lock as before.
Slide the wall plate over horizontal run before at-
taching the horizontal run to the elbow. Fasten wall
plate to wall.
4. For CFM Vent Pipe only: If necessary, measure
to determine the vertical length (X) of pipe required
from the adapter pipe to the wall cutout centerline,
including a 2" overlap at the joint. (Fig. 26) use a
hacksaw or tin snips to trim the pipe as needed.
Fig. 26 Determine the vertical pipe length.
5. Install first the inner then the outer straight pipe
section(s), trimmed end down, to the point of the el-
bow. Drill 3 holes through each joint and fasten with
sheet metal screws.
20004188
Sleeve
#8 Sheet
Metal Screws
Firestop
ZCS103
X
ST652
Radiance Direct Vent /Natural Vent Gas Heater
6. Install the elbow using 3 sheet metal screws at each
joint.
7. Measure, and cut if needed, the appropriate length
of pipe section needed to make the connection
through the wall. Include a 2" overlap; i.e. from the
elbow to the outside wall face, about 2" or the dis-
tance required if installing a second 90° elbow. (Fig.
27)
8. Slip the wall plate and trim collar over the interior
end of the horizontal pipe and install into the wall
sleeve. Seal the joint inside the wall plate if needed
to keep cold air from being drawn into the home.
9. Connect the horizontal pipe to the elbow. Fasten the
wall plate to the pipe with three sheet metal screws.
Slide the trim collar up against the wall plate to cover
the screws. (Fig. 28)
Fig. 27 Measure the horizontal length.
Wall
Sleeve
ST216
Fig. 28 Install the horizontal pipe and wall plate parts.
10. For both CFM and DuraVent Systems: Install the
vent terminal. (Fig. 29) Apply high temperature seal-
ant one inch from the ends of the inner and outer
ST216
collars. Guide the inner and outer vent termination
install pipe thru wall
collars into the adjacent pipes. Double check that
12/6/99 djt
the vent pipes overlap the collars by 2". Fasten the
termination to the wall with the screws provided, and
caulk the joint with weatherproof sealant.
X
Trim Collar
ST215
measure thru wall
12/6/99 djt