Commissioning

7 Commissioning
7.1 Commissioning the Inverter
1. Check for firm positioning on the wall
(see section 4 "Mounting the Device" (page 16)).
2. Check for correct country configuration
(see section 5.3.2 "Checking the Country Standard" (page 25)).
3. Check for correct connection of the AC grid cable
(see section 6.2 "Connection to the Public Grid (AC)" (page 39)).
4. Check for correct connection of the DC cables (PV strings)
(see section 6.3 "Connection of the PV Generator (DC)" (page 45)).
5. Close unnecessary DC inputs wit the DC plug connectors and sealing plugs
(see section 6.3.4 "Connecting the PV Generator (DC)" (page 49)).
6. Check whether all enclosure openings are closed.
7. Check whether the enclosure lid is firmly screwed in place.
8. Check for correct connection of the Quick Module.
9. Firmly connect the Electronic Solar Switch.
10. Check for correct design of the line circuit breaker.
11. Switch on the line circuit breaker.
12. If a multi-function relay is connected, switch on the multi-function relay power supply.
Self test in accordance with ENEL directive for initial start-up
(applies to Italy only)
The Italian standard prescribes that an inverter can only operate on the public grid after
the disconnection times for overvoltage, undervoltage, minimum frequency and maximum
frequency have been checked.
If you have configured the Enel-GUIDA country data set, start the self-test as described in
section 7.3 "Self-Test in accordance with ENEL Directive, Ed. 1.1 (Applies to Italy only)"
(page 54). The test takes approx. 3 minutes.
52
SB20_25_30HF-IEN102911
SMA Solar Technology AG
Installation Guide

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

2000hf

Table of Contents