Preparing The Site; Site Selection Criteria - Dell C7008 Installing

High performance switch/router system.
Hide thumbs Also See for C7008:
Table of Contents

Advertisement

Preparing the Site

Site Selection Criteria

Before beginning the installation process, make sure that the area where you intend to install your C7008/
C300 meets the following safety requirements:
• It is in a restricted access area.
• It is in a dry, clean, well-ventilated, temperature-controlled room, that is away from heat sources such as
hot air vents or direct sunlight.
• It is away from sources of severe electromagnetic noise.
• Power supply is adequate for power requirements.
Connect the C-Series System to the appropriate branch circuit protection as defined by local
electrical codes.
WARNING: The C7008/C300 does not have a main disconnect device installed. It is the responsibility of the
installer to provide a suitable disconnecting device in the building installation and ensure that it is located/
installed near the equipment and is easily accessible.
• It is positioned in a rack with adequate space in the front, rear, and sides of the unit for proper
ventilation, access to cables, and maintenance access.
• Allow at least six inches (16 cm) of clearance around the side intake and exhaust vents.
• Allow at least 12 inches (30.5 cm) between two C7008s/C300s or an C7008/C300 and another
side airflow chassis.
• Allow at least 18 inches in the front and 20 inches in the rear of the rack.
NOTE: The C-Series does not have an air filter, so take special care in making sure that the installation site
and the chassis itself are cleaned regularly.
Installing and Maintaining the C300 System
3
13

Advertisement

Table of Contents
loading

This manual is also suitable for:

C300

Table of Contents