Installing The Exp300 In A Tower - IBM Netfinity EXP300 Hardware Maintenance Manual

Type 3531
Hide thumbs Also See for Netfinity EXP300:
Table of Contents

Advertisement

Statement 4
≥18 kg (37 lbs)
CAUTION:
Use safe practices when lifting.
7. Slide the expansion unit into the rack, and insert the M6 screws 1 . Do not
overtighten the M6 1 screws.
8. Tighten the rear screws 2 .
9. Verify that option switches 1 and 2 (inside the switch card) are set to off (see
"Setting the interface options and ID settings" on page 10 for more information).
10. Install hard disk drives and power supplies in the EXP300 expansion unit
according to "Locations" on page 8; then, return here to complete the installation.
11. Continue with "Completing the installation" on page 35.

Installing the EXP300 in a Tower

®
The IBM
Netfinity
storage expansion unit into a tower mounted installation. You will need a flat-blade
screwdriver and a phillips screwdriver to install the EXP300. Use the mounting
hardware that comes with your unit to secure it in the enclosure.
Before installing the expansion unit you must:
≥32 kg (70.5 lbs)
®
EXP300 Rack-to-Tower Conversion Kit converts the EXP300
≥55 kg (121.2 lbs)
Netfinity EXP300 Type 3531
29

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Netfinity EXP300 and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents