Mantel and Top Trim Clearances
Measure clearances from the finished floor of the fire-
place opening.
A:
48 1/2" (1232)
B:
47"
(1194)
C:
45 1/2" (1156)
D:
44"
(1118)
E:
42 1/2" (1080)
F:
41"
(1041)
NOTE: MANTEL AND TOP TRIM CLEARANCES ARE NOT AF-
FECTED BY THE USE OF THE 2" RISER BAR.
Leg Leveler Bolts and Brackets
This feature enables greater installation flexibility
beyond eliminating problems caused by irregularities
in the hearth floor.
Install the leveling bolts all the way into the bolt
brackets. The leveling bolts may be extended from the
mounting brackets no more than 1/2". See fig. 6.
The firebox may be further raised, in 1/2" incre-
ments, up to 2 1/2" more (max. 3" total) by adjusting
the height of the leveling bolt mounting brackets. Fig. 7
.
Clearance to Combustibles
When raising the firebox up to 2", mantel and hearth
clearances remain unchanged from those specified in fig. 5.
NOTE: IF RAISING THE UNIT MORE THAN 2 INCHES,
ADD I INCH TO THE BASELINE CLEARANCES
SPECIFIED ABOVE.
Stabilizer Bar
In some instances, raising the height of the unit may
require installing the insert with the Stabilizer Bar
supplied with the insert. See page 24 of this manual
for further details.
Power Requirement
This appliance requires 120 V AC power to operate the
blower, accent lamps, and electronic ignition.
Four, AA batteries provide back-up power in case
of a power outage.
A
B
C
D
E
Figure 5. Baseline Mantel and Trim clearance requirements.
Level-
ing Bolt
Mounting
Brackets
Figure 6. The leveling bolts should not be extended
further than 1/2".
Figure 7. The bolt mounting brackets may be
extended up to 2 1/2". With maximum extension of
both bolts and brackets, the firebox may be raised a
total of 3".
139177_Rev_C July 11, 2010
MANTEL
AREA
1”
3.5”
5.5”
7.5”
9.5”
11.5”
F
1/2” max
3” max.
9

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents