• Adjust the termination cap to its final exterior posi-
tion on the building and interlock the flue sections.
WARNING: THE TERMINATION CAP
!
MUST BE POSITIONED SO THAT THE
ARROW IS POINTING UP.
• Use a high-temperature sealant gasket to seal be-
tween the pipe and exterior firestop.
1" (25mm)
7-1/2"
(192mm)
MINIMUM
FIGURE 1.27 Termination Cap
For Vertical Terminations - To locate the flue and
install the flue sections:
• Locate and mark the flue center point on the un-
derside of the roof, and drive a nail through the
center point.
• Make the outline of the roof hole around the center
point nail.
• The size of the roof hole framing dimensions de-
pend on the pitch of the roof. There MUST BE a 1-
inch (25 mm) clearance from the vertical flue pipe
to combustible materials.
• Mark the roof hole accordingly.
• Cover the opening of the installed flue pipes.
• Cut and frame the roof hole.
• Use framing lumber the same size as the roof rafters
and install the frame securely. Flashing anchored
to the frame must withstand heavy winds.
• Continue to install concentric flue sections up
through the roof hole and up past the roof line until
you reach the appropriate distance above the roof.
18
Heat & Glo • 6000TRSI-AUC • 2078-900 Rev.C • 7/06
CAUTION: FOLLOW THE REQUIREMENTS OF
THE AGA GAS INSTALLATION CODE FOR
MINIMUM HEIGHT REQUIREMENTS ABOVE THE
ROOF.
To seal the roof hole, and to divert rain and snow
from the flue system:
• Attach a flashing to the roof using nails, and use
a non-hardening mastic around the edges of the
flashing base where it meets the roof.
• Attach a storm collar over the flashing joint to form
a water-tight seal. Place non-hardening mastic
around the joint, between the storm collar and
the vertical pipe.
• Slide the termination cap over the end of the flue
pipe and rotate the pipe clockwise 1/4 turn.
GAS LINE
ACCESS
FIGURE 1.28
D. CONNECTING THE GAS SUPPLY
The gas is introduced to the appliance on the left
hand side. See Figure 1.28.
After the gas pipe installation is complete, check care-
fully all gas connections for leaks with a commer-
cially-available, noncorrosive leak check solution. Be
sure to rinse off all leak check solution following test-
ing. DO NOT USE AN OPEN FLAME.
NOTE:
THE GAS SUPPLY LINE SHOULD BE
PURGED OF ANY TRAPPED AIR PRIOR TO THE
FIRST FIRING OF THE UNIT.