B. Assemble Vent Sections (SLP Pipe Only)
To attach the first vent component to the starting collars
of the appliance:
• Lock the vent components into place by sliding the pipe
section onto the collar.
• Align the seam of the pipe and seam of collar to allow
engagement. Rotate the vent component to lock into
place. Use this procedure for all vent components. See
Figure 10.5.
• Slide the gasket over the first vent section and place it
flush to the appliance. This will prevent cold air infiltra-
tion. High temperature caulk may be used to hold the
part in place.
• Continue adding vent components, locking each
succeeding component into place.
• Ensure that each succeeding vent component is securely
fitted and locked into the preceding component.
Commercial, Multi-family (Multi-level exceeding two sto-
ries), or High-Rise Applications
For Installation into a commercial, multi-family (multi-level
exceeding two stories) or high-rise applications: All outer
pipe joints must be sealed with high temperature silicone,
including the slip section that connects directly to the hori-
zontal termination cap.
• Apply a bead of silicone sealant inside the female outer
pipe joint prior to joining sections. See Figure 10.1.
• Only outer pipes need to be sealed. All unit collar, pipe,
slip section, elbow and cap outer flues shall be sealed
in this manner, unless otherwise stated.
WARNING! Risk of Fire or Explosion! DO NOT break
silicone seals on slip sections. Use care when remov-
ing termination cap from slip pipe. If slip section seals
are broken during removal of the termination cap, vent
may leak.
Note: Align seams to engage pipe,
then rotate counterclockwise to lock
Figure 10.5 Adding Venting Components
46
Heat & Glo • 550TRSI-AUF, 550TRSILP-AUF • 2079-980 Rev. R • 2/13
C. Assemble Slip Sections
• Slide the inner flue of the slip section into the inner flue
of the pipe section and the outer flue of the slip section
over the outer flue of the pipe section. See Figure 10.6.
• Slide together to the desired length.
Figure 10.6 Slip Section Pilot Holes
• Maintain a 1-1/2 in. (38 mm) overlap between the slip
section and the pipe section.
• Secure the pipe and slip section with two screws no
longer than 1/2 in. (13 mm), using the pilot holes in the
slip section. See Figure 10.7.
Figure 10.7 Screws into Slip Section
• Continue adding pipe as necessary following instructions
in "Assembling Pipe Sections."
NOTICE: If slip section is too long, the inner and outer
flues of the slip section can be cut to the desired length.
NOTICE: When installing a vent system with an HRC
termination cap, all pipe system joints shall be sealed using
a high temperature silicone sealant.
• Apply a bead of silicone sealant inside the female outer
pipe joint prior to joining sections.
• Only outer pipes are sealed, sealing the inner flue is not
required.
• All unit collar, pipe, slip section, elbow and cap outer
flues shall be sealed.