Trion AIR BOSS 60 Series Installation, Operation & Service Manual

60 series field assembled electronic air cleaner without integral washing system

Advertisement

Quick Links

Field Assembled
ELECTRONIC
AIR CLEANER
AIR BOSS Model 60 Series
without
Integral Washing System
INSTALLATION
OPERATION
SERVICE
For Model Numbers
60- ___-01
Electrostatic Precipitators for
Commercial & Industrial
Applications
101 McNeill Road Sanford, NC 27330
(919) 775-2201 Fax: (919) 774-8771 (800) 884-0002
www.trioninc.com
MANUAL Form No. 61-0147B
Sept 01

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the AIR BOSS 60 Series and is the answer not in the manual?

Questions and answers

Summary of Contents for Trion AIR BOSS 60 Series

  • Page 1 Field Assembled ELECTRONIC AIR CLEANER AIR BOSS Model 60 Series without Integral Washing System INSTALLATION OPERATION SERVICE For Model Numbers 60- ___-01 Electrostatic Precipitators for Commercial & Industrial Applications 101 McNeill Road Sanford, NC 27330 (919) 775-2201 Fax: (919) 774-8771 (800) 884-0002 www.trioninc.com MANUAL Form No.
  • Page 2: Table Of Contents

    TABLE OF CONTENTS SECTION I DESIGN For The System Design Engineer Page 1. General Description ............................3 2. System Design and Floor Layout ........................ 3 3. Outdoor Installations ............................ 4 SECTION II INSTALLATION For The Installing Contractor 1. Unpack and Inspect............................4 2.
  • Page 3: Section I Design

    Serious consideration should be given to any deviation Note: Trion Tridex Detergent is specially formulated from the suggested design, which would result in for use with Trion electronic air cleaners. Use of improper drainage, leakage, air bypass and mounting. other cleaners and detergents, not specifically...
  • Page 4: Outdoor Installations

    A, B to B, etc. The required fasteners are packaged and marked for the framework. (D) After the outside frame structure is complete, Contact the local Trion Sales Office or the factory if position and secure the intermediate cell supports. questions arise, or any additional information is The side to receive the air bypass strips marked required.
  • Page 5: Install Ionizing-Collecting Cells

    will be under negative pressure and should be made air The high voltage wiring consists of interconnecting tight to prevent infiltration of contaminated air. the ionizing-collecting cells into banks with bus bars, then wiring each bank of interconnected cells After the ductwork has been installed, clear remaining to its corresponding power supply with the high material or debris from inside ducts and bottom of voltage cable.
  • Page 6: Check Out For System Start-Up

    B. The drain line from the Trion drain basin is clear and contaminant. completely connected to its point of termination. C. Supply line power is available and electrical wiring 2. General Description...
  • Page 7: Routine Maintenance

    LED display for kilovolt and milliampere readings. The milliammeter should be observed on a routine D. Be sure that the drain lines from the Trion cabinet basis to be sure that it is reading within the drain basin are completely connected and properly prescribed operating range as marked on the data terminated.
  • Page 8: Troubleshooting

    At the start of the cleaning process, electrical The most common outage is a short in the switches that could be accidentally activated shall secondary circuit and is best located through the be locked out. Components of the fire suppression process of elimination.
  • Page 9: Spare Parts

    For specific recommendations, consult the Trion factory (2) When the short is isolated to a cell tier, remove or nearest Sales Office. Consideration, however, should all the cells within the tier and visually check the be given to stocking the following components;...
  • Page 10: Troubleshooting Reference Chart

    Troubleshooting Reference Chart PROBLEM/ PROBABLE LOCATION REASON - CORRECTION SYMPTOM CAUSE Ionizing Section of Cell Dirty insulator(s) – Clean Defective insulator(s) – Replace Foreign Object Between Ionizing Bar and Ground electrode - Remove Collecting Section of Cell Dirty insulator(s) - Clean Defective insulator(s) –...
  • Page 25: Figure

    Model 60 Control Schematic THIS PAGE INTENTIONALLY LEFT BLANK DETAILED SCHEMATIC DRAWINGS WILL BE PROVIDED BASED ON THE SIZE AND CONFIGURATION OF YOUR UNIT ORDERED. FIGURE 11...
  • Page 26 Model 60 Field Wiring THIS PAGE INTENTIONALLY LEFT BLANK DETAILED FIELD WIRING DRAWINGS WILL BE PROVIDED BASED ON THE SIZE AND CONFIGURATION OF YOUR UNIT ORDERED. FIGURE 12...