Start-Up Checklist - Bryant 548F Installation, Start-Up And Service Instructions Manual

Sizes 036-072 3-6 tons single package rooftop standard-efficiency heat pump units
Hide thumbs Also See for 548F:
Table of Contents

Advertisement

I. PRELIMINARY INFORMATION
MODEL NO.: _______________________________________
DATE:______________________________________________
JOB LOCATION:____________________________________
II. PRE-START-UP (insert checkmark in box as each item is completed)

VERIFY THAT CONDENSATE CONNECTION IS INSTALLED PER INSTALLATION INSTRUCTIONS

CHECK ALL ELECTRICAL CONNECTIONS AND TERMINALS FOR TIGHTNESS

CHECK THAT INDOOR AIR FILTER IS CLEAN AND IN PLACE

VERIFY THAT UNIT INSTALLATION IS LEVEL

CHECK FAN WHEEL AND PROPELLER FOR LOCATION IN HOUSING/ORIFICE AND SETSCREW
TIGHTNESS

CHECK PULLEY ALIGNMENT AND BELT TENSION REFER INSTALLATION INSTRUCTIONS
(Size 072 Standard Motor and Sizes 036-060 Alternate Motor and Drives)

ENSURE BELT TENSION IS CORRECT AND BLOWER PULLEYS ARE PROPERLY ALIGNED
III. START-UP:
ELECTRICAL
SUPPLY VOLTAGE
COMPRESSOR AMPS
INDOOR-FAN AMPS
TEMPERATURES AND PRESSURES
OUTDOOR-AIR TEMPERATURE
RETURN-AIR TEMPERATURE
COOLING SUPPLY AIR
(COOLING MODE)
REFRIGERANT SUCTION
SUCTION LINE TEMPERATURE
REFRIGERANT DISCHARGE
LIQUID LINE TEMPERATURE

VERIFY THAT 3-PHASE SCROLL COMPRESSOR IS ROTATING IN THE CORRECT DIRECTION

VERIFY REFRIGERANT CHARGE USING COOLING CHARGING CHARTS ON PAGE 41 (COOLING MODE) ONLY).
UNIT MUST OPERATE A MINIMUM OF 15 MINUTES BEFORE ADJUSTING CHARGE.
Copyright 2000 Bryant Heating & Cooling Systems

START-UP CHECKLIST

(Remove and Store in Job File)
L1-L2
L2-L3
L1
L2
L1
L2
DB
DB
DB
PSIG
F
PSIG
F
SERIAL NO.: ________________________________________
TECHNICIAN:_______________________________________
L3-L1
L3
L3
WB
WB
CL-1
CATALOG NO. 5354-808