Install Controller Batteries

The two battery packs included with the controller module must be installed before the controller module is
installed in the disk array.
1.
Remove the battery cover latch and then remove the RFI shield (if necessary, you can use a flat-bladed
screwdriver to remove the RFI shield).
2.
Install both battery packs, and connect the cables as shown in panel 4 of Figure 5.
3.
Reinstall the RFI shield and the battery cover latch.
CAUTION
Make sure you reinstall the battery cover latch carefully, so each of the locking tabs
(items 1 and 2 in panel 5 of Figure 5) slide beneath the battery compartment. If the
battery cover latch is not secured properly, it could prevent the removal of the controller
module once it is installed in the disk array enclosure.

Figure 5. Installing Controller Batteries