DSA 2 MAXI Substation
2. Lifting with a crane
It is possible to screw up lifting eyes in the top corners after remov-
ing detachable metal round pieces from the roof. This way substa-
tion can be lifted up by using straps.
5.5

Installation place

The installation place and the pipe connections for DSA 2 MAXI
substation can be planned in beforehand due to standardized
sizing.
The upwards oriented connections enable installation e.g. close to
the wall. Since the hot surfaces are hidden underneath the cover it
is possible to use the boiler room also for some other activities.
10 DEN-SMT/PL