2.1 Check System Installation & Power On
All components were installed according to the installation guides, please check the
following highlighted installation locations:
Power on the system according to the MIN 3000-11400TL-XH-US Quick Guide which is
included in the inverter package/box.
Ø
ARO Battery Wiring Diagram please refer to ARO 6.6-19.8H-C1-US Quick Guide QR
code.
Ø
APX Battery Wiring Diagram please refer to
code.
Ø
LG Battery Wiring Diagram please refer to LG RESU Prime Quick Guide QR code.
Ø
ATS 11400T-US Wiring Diagram please refer to ATS-US Series Quick Guide QR code.
ARO Battery
2.2.1 Installation and Wiring of Electric Meter SM-US-200
a) Meter Mounting
Ø
The meter should be mounted in a Power Distribution Box.
Ø
Mount the meter on a 35mm DIN rail.
b) CT Installation
Install the two CTs with the Arrow pointing to the LOAD.
Make sure the CT of L1 matched L1 input of the Service Panel that also match the L1 to
Ø
the inverter.
Make sure the CT of L2 matched L2 input of the Service Panel that also match the L2 to
Ø
the inverter.
c) Meter Wiring
Ø
When connecting the meter to the inverter, refer to the connection diagram below.
Power on the system 2
Fig 2.1 Inverter Box Wiring Diagram
APX Battery
APX 5.0-30.0P-S0-US
LG Battery
Quick Guide
QR
ATS-US
Fig 2.2
4