BUSCH SECO SV 1008 C Instruction Manual

BUSCH SECO SV 1008 C Instruction Manual

Dry-running rotary vane vacuum pumps
Hide thumbs Also See for SECO SV 1008 C:

Advertisement

Quick Links

SECO
Dry-running Rotary Vane Vacuum Pumps
SV 1008 C
Instruction Manual
0870135648 | A0002_en-US | Original instructions
5/21/2024

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the SECO SV 1008 C and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for BUSCH SECO SV 1008 C

  • Page 1 SECO Dry-running Rotary Vane Vacuum Pumps SV 1008 C Instruction Manual 0870135648 | A0002_en-US | Original instructions 5/21/2024...
  • Page 2: Table Of Contents

    Table of Contents​ Table of Contents Safety ..................................Product Description ............................. Operating Principle ............................. Intended Use ............................... Standard Features............................... 2.3.1 Motor Thermal Protection........................Optional Accessories............................2.4.1 Inlet Filter .............................. 2.4.2 Hose Nipple ............................2.4.3 Vacuum Regulating Unit........................2.4.4 Silencer ..............................2.4.5 Handle..............................
  • Page 3: Safety

    Safety Prior to handling the machine, this instruction manual should be read and understood. If anything needs to be clarified, please contact your Busch representative. Read this manual carefully before use and keep for future reference. This instruction manual remains valid as long as the customer does not change anything on the product.
  • Page 4: Product Description

    2 | Product Description​ Product Description MTB / CC Description Suction connection Discharge connection Accessory connection (vacuum) Capacitor Directional arrow Motor terminal box MTB / CC Motor terminal box cable connection Nameplate NOTE Technical term. In this instruction manual, we consider that the term ‘machine’ refers to the ‘vacuum pump’. NOTE Illustrations.
  • Page 5: Operating Principle

    Conveying of other media leads to an increased thermal and/or mechanical load on the machine and is permissible only after a consultation with Busch. The machine is intended for the placement in a non-potentially explosive environment.
  • Page 6: Standard Features

    2 | Product Description​ Standard Features 2.3.1 Motor Thermal Protection Single-phase motors are equipped with a thermal protection switch to protect the machine against overload. Three-phase motors are not equipped with a thermal protection switch. Optional Accessories 2.4.1 Inlet Filter The inlet filter (IF) protects the machine against dust and other solids in the process gas.
  • Page 7: Accessories Description

    Product Description​ | 2 2.4.6 Accessories Description Description Direction arrow (DA) Capacitor (CAP) Handle (HD) (optional) Feets with rubber pads (FRP) Vanes (VA) (x 3) Internal inlet filter (IIF) Internal discharge filter (IDF) Vacuum regulation unit (vacuum regu- lating valve (VRV) with vacuum gauge (VG)) (optional) Non-return valve (NRV) (optional) Silencer (SI) (optional)
  • Page 8: Transport

    3 | Transport​ Transport ● To find out the weight of the machine, refer to the chapter Technical Data [➔ 24] or the name- plate (NP). ● Check the machine for transport damage. If the machine is secured to a base plate: ●...
  • Page 9: Storage

    Storage​ | 4 Storage ● Seal hermetically all apertures with the caps provided with the machine, or with adhesive tape if the caps are no longer available. ● Store the machine indoors, in a dry place, away from dust and vibrations and if possible, in original packaging, preferably at temperatures between -10 ...40°C.
  • Page 10: Installation

    5 | Installation​ Installation Installation Conditions NOTICE Use of the machine outside of the permitted installation conditions. Risk of premature failure! Loss of efficiency! ● Make sure that the installation conditions are fully respected. Description ~ 2 cm ~ 2 cm ~ 2 cm ~ 2 cm ●...
  • Page 11 Installation​ | 5 If the machine is installed at an altitude greater than 1000 meters above sea level: ● Contact your Busch representative, the motor should be derated or the ambient temperature limited. Instruction Manual SECO SV 1008 C_EN_en 11 | 28...
  • Page 12: Connecting Lines / Pipes

    ● Make sure that the diameter of the connection lines over the entire length is at least as large as the connections of the machine. In case of long connection lines, it is recommended to use larger diameters to avoid a loss of effi- ciency. In this case, please contact your Busch representative. 5.2.1 Suction Connection NOTICE Ingress of foreign objects or liquids.
  • Page 13: Electrical Connection

    ● If the machine is equipped with a power connector, install a residual current protective device to protect persons in case of a defective insulation. ● Busch recommends installing a type B residual protective device suitable for the electrical in- stallation.
  • Page 14: Wiring Diagram Three-Phase Motor

    6 | Electrical Connection​ ● Provide a lockable disconnect switch on the power line so that the machine is completely secured during maintenance tasks. ● Provide an overload protection according to EN 60204-1 for the motor. ● Connect the protective earth conductor. ●...
  • Page 15: Wiring Diagram Single-Phase Motor

    Electrical Connection​ | 6 Star connection (high voltage): Wiring Diagram Single-Phase Motor L1 = Phase 1; N = Neutral; PE = Ground = Capacitor = Standard single-phase motor – U = Main phases – Z = Auxiliary phases Instruction Manual SECO SV 1008 C_EN_en 15 | 28...
  • Page 16: Commissioning

    7 | Commissioning​ Commissioning NOTICE Lubricating a dry running machine (compression chamber). Risk of damage to the machine! ● Do not lubricate the compression chamber of the machine with oil or grease. CAUTION During operation the surface of the machine may reach temperatures of more than 70°C. Risk of burns! ●...
  • Page 17: Maintenance

    Risk of injuries! Risk of premature failure and loss of efficiency! ● Maintenance work must only be executed by qualified personnel. ● Respect the maintenance intervals or ask your Busch representative for service. NOTICE Using inappropriate cleaners. Risk of removing safety stickers and protective paint! ●...
  • Page 18: Maintenance Schedule

    8 | Maintenance​ Maintenance Schedule The maintenance intervals depend very much on the individual operating conditions. The intervals given below are considered as starting values which should be individually shortened or extended as appropriate. Particularly harsh applications or heavy duty operation, such as high dust loads in the environment or in the process gas, other contamination or ingress of process material, can make it necessary to shorten the maintenance intervals significantly.
  • Page 19 Maintenance​ | 8 Description Busch genuine spare parts: 3 x vanes 1 x Inlet filter cartridge (IIF) : (VA): 0722133118 0532133447 1 x Discharge filter cartridge (IDF) : 0532133447 Description 4 mm hex key Instruction Manual SECO SV 1008 C_EN_en...
  • Page 20: Overhaul

    ● Decontaminate the machine as much as possible and state the contamination status in a ‘Declaration of Contamination’. Busch will only accept machine accompanied by a signed, fully completed and legally binding "decla- ration of contamination", downloadable from the following link: buschvacuum.com/declaration-of- contamination.
  • Page 21: Decommissioning

    Decommissioning​ | 10 Decommissioning DANGER Live wires. Risk of electrical shock! ● Electrical installation work must only be executed by qualified personnel. CAUTION Hot surface. Risk of burns! ● Before doing anything that requires touching the machine, let it cool down first. ●...
  • Page 22: Spare Parts

    Use of non-Busch original spare parts. Risk of premature failure! Loss of efficiency! ● Use only original Busch spare parts, consumables and supplies to ensure correct operation of the machine and to validate the warranty. If other parts are required: ●...
  • Page 23: Troubleshooting

    The internal filters (IIF & IDF) ● Replace the internal filters are partially clogged. (IIF & IDF). For resolution of problems not listed in the troubleshooting table, please contact your Busch repre- sentative. Instruction Manual SECO SV 1008 C_EN_en 23 | 28...
  • Page 24: Technical Data

    13 | Technical Data​ Technical Data SV 1008 C Nominal pumping speed m³/h 7.3 / 8.8 (50 Hz) / (60 Hz) Ultimate pressure hPa (mbar) Nominal motor rating 0.25 / 0.30 (50 Hz) / (60 Hz) Nominal motor speed min⁻¹ 3000 / 3600 (50 Hz) / (60 Hz) Sound pressure level (ISO 2151), KpA = 3 dB...
  • Page 25: Eu Declaration Of Conformity

    EU Declaration of Conformity This Declaration of Conformity and the CE-markings affixed to the nameplate are valid for the machine within the Busch scope of delivery. This Decla- ration of Conformity is issued under the sole responsibility of the manufacturer.
  • Page 26: Uk Declaration Of Conformity

    UK Declaration of Conformity This Declaration of Conformity and the UKCA-markings affixed to the nameplate are valid for the machine within the Busch scope of delivery. This Dec- laration of Conformity is issued under the sole responsibility of the manufacturer.
  • Page 27 ​ N otes Notes Instruction Manual SECO SV 1008 C_EN_en 27 | 28...
  • Page 28 With a network of over 60 companies in more than 40 countries and agencies worldwide, Busch has a global presence. In every country, highly competent local personnel delivers custom-tailored support backed by a global network of expertise. Wherever you are.