Table 12. Initial start-up readiness checklist (continued)
Start-Up Readiness Dimension
☐ ☐
Check the box if heat pump system includes any remote panels (city water switchover, remote control panel, or customer supplied control devices). If so,
voltage drops are likely to occur. Measure and record all control voltages:
List devices: Voltage 1=_____________________ Voltage 2=_____________________ Voltage 3=___________________
Check the box if there are any field-supplied wiring junction boxes located between the heat pump and any remote panels.
Check the box if there are any splices made in the field-supplied wiring junction boxes.
Check the box if there are any customer-supplied devices connected to the heat pump wiring.
List devices: ______________________________________________________________________________________
Check the box if there are any Trane remote devices connected to the heat pump wiring.
Check the box if voltage drops are detected.
Check the box if the appropriate water/glycol mixture has been added to the heat pump.
Check the box if all Heat Pump modules are installed with minimum clearances available from all sides.
Check the box if refrigeration gauges are indicating equal refrigerant pressures.
Check the box if chilled water lines from Heat Pump to customer's equipment are permanently connected.
Check the box if chilled water lines have been flushed clean of mud, slag, and other construction debris.
Check the box if all chilled water line filters and strainers are clean.
Check the box if chilled water lines have been leak tested according to pre-start-up instructions.
Check the box if heat pump reservoir (if included) is at operating level with correct water/glycol mixture.
Check the box if high voltage wiring is installed, tested, and functional.
Check the box if all water, refrigeration, and electrical connections between heat pump modules are completed.
Check the box if all control wiring between modular heat pumps is installed, tested, and functional.
Check the box if control wiring is complete, including any remote interface panel or special-purpose wiring.
Check the box if all responsible installing contractors and sub-contractors have been notified to have representatives available on site to provide technical
support for the initial start-up procedure.
Check the box if full load will be available for heat pump on the initial start-up date.
Touchscreen Interface Panel: Record version and date of the software loaded into the touchscreen interface panel:
Version: ____________________________________ Date: ________________
Note: To view the software version, from the home screen, press the software button on the System Control screen.

Start-Up

As part of a continuous commitment to quality, initial start-