Figure 1-102 Installing a signal cable between the UPS and the SmartLi
(1) Monitoring interface unit in the master SmartLi cabinet
----End

1.10 Installing a Top Enclosure Frame

If cables are routed from the top or bottom, install a top enclosure frame.

1.10.1 Top Cable Routing

Step 1 Remove the connecting kits from both sides of the UPS cabinet top.
Figure 1-103 Removing cabinet connecting kits
Step 2 Remove the connecting kits from both sides of the inductor cabinet top.