Bottom Cable Routing - Huawei UPS5000-H-1200 kVA-NTN Quick Manual

Table of Contents

Advertisement

UPS5000-H-1200 kVA-NTN
Quick Guide (480 V, 100 kVA Power Modules)

1.10.2 Bottom Cable Routing

Step 1 Remove the connecting kits from both sides of the inductor cabinet top.
Figure 1-112 Removing cabinet connecting kits
Step 2 Install a top frame on the top of the UPS cabinet and the bottom cabling cabinet.
Figure 1-113 Installing a top frame
Step 3 Install a top frame on the top of the inductor cabinet.
Issue 01 (2023-03-20)
Copyright © Huawei Technologies Co., Ltd.
1 Installation and Cable Connection
81

Advertisement

Table of Contents
loading

Table of Contents