Download Print this page

AlphaESS SMILE-G3-S3.6 Comissioning Hardware

Hide thumbs Also See for SMILE-G3-S3.6:

Advertisement

Quick Links

V01
COMMISSIONING GUIDE & REPORT
SMILE-G3-S3.6 / S5 / B5

Advertisement

loading
Need help?

Need help?

Do you have a question about the SMILE-G3-S3.6 and is the answer not in the manual?

Questions and answers

Summary of Contents for AlphaESS SMILE-G3-S3.6

  • Page 1 COMMISSIONING GUIDE & REPORT SMILE-G3-S3.6 / S5 / B5...
  • Page 2: Checking Before Power-On

    Commissioning Procedures 1. Commissioning Procedures 1.1. Checking Before Power-On Check Item Acceptance Criteria The mounting space is proper, and the Mounting environment mounting environment is clean and tidy, without foreign objects. Battery pack and The battery pack and inverter are mounted inverter mounting correctly, securely, and reliably.
  • Page 3 1.3.1. WiFi Configuration This section is for users who have an energy storage system with a WiFi module. AlphaESS App is able to configure the network, set system basic parameter, monitor system operation status and check configuration information. Click ”WiFi...
  • Page 4 Commissioning Procedures Select the WiFi Select the WiFi Module Signal Router Signal ALXXXX 12345678 This is default pass code Enter WiFi router password The system will not be able to connect to the internet without WiFi configuration.
  • Page 5 Commissioning Procedures 1.3.1.1 Basic Parameters Settings DC Mode Three mode options: DC/AC/Hybrid Storage PV capacity: PV capacity on the energy storage inverter side 5 kW Storage PV Capacity On the grid side, if only a CT is installed, please select CT for grid side. If the grid meter is installed, please select Meter for grid side.
  • Page 6 Commissioning Procedures AC Mode Three mode options: DC/AC/Hybrid PV capacity on the PV-inverter (on-grid) side On the grid side, if only a CT is installed, please select CT for grid side. If the grid meter is installed, please select Meter for grid side. If this meter is a CT meter and the CT ratio is not 1, please select CT below and input the Meter CT Ratio.
  • Page 7 Commissioning Procedures Hybrid Mode Three mode options: DC/AC/Hybrid Hybrid PV capacity on the PV-inverter (on-grid) side Storage PV capacity: PV capacity on the energy storage inverter side 5 kW Storage PV Capacity On the grid side, if only a CT is installed, please select CT for grid side. If the grid meter is installed, please select Meter for grid side.
  • Page 8 Commissioning Procedures The safety regulation must be set correctly If you select a safety regulation which is not valid for your country and purpose, it will cause a disturbance in the energy storage system and lead to problems with the grid operator.
  • Page 9 Commissioning Procedures  Switch on the PV switch on the energy storage inverter if there is any and AC breaker on the PV-inverter if there is any.  Switch off all the loads to see the battery charging status and the inverter LED (“SYSTEM”)* will be solid on green.
  • Page 10 Commissioning Procedures If the electrical appliance on backup side can work  normally, it means that the wiring of the backup has been connected correctly. During commissioning, if the LED indictors on the display panel of the inverter or the battery pack show red, please refer to chapter troubleshooting.
  • Page 11 Commissioning Procedures 1.4.2. Register as an Installer If you don’t have an installer account, please register first. Get the license No. from your distributor. If you already have an installer account, please log in directly. 1.4.3. Install New System If you have “installed” the new system already or want to install it later, please directly to the Section 1.3 WiFi Module Configuration and Parameter Settings.
  • Page 12 Commissioning Procedures You can find the SN and check code on the label of the Battery with EMS. Scan or type in. After login, click “Install new system” Australian Installer Please enter your installer account and click “Install New System” to bind the system to your account and set the system.
  • Page 13 Commissioning Procedures field, which has six fixed options (NSW, QLD, VIC, SA, TAS, WA). If SA is selected for Region, two more fields are added which are Agent and NMI. Fields that are not marked "optional" need to be filled in. Click "Next"...
  • Page 14 Commissioning Procedures Step2 Select “ON” to Charge Batteries from Grid” please set the “Charging period 1” for the time and the SOC would be 100 under this operation. Step3 The relative value should be like this:Load = PV ± GRID – Battery Battery should be in charging...
  • Page 15 Commissioning Procedures 1.5.2. Check the PV Generation and Discharging Function of the Product Step1: Please switch off the PV switch on the energy storage inverter and the AC breaker on the PV inverter if there is any. Switch on some larger loads to see the battery discharging status.
  • Page 16 Commissioning Procedures If the electrical appliance can work normally, it means that the wiring of the  backup has been connected correctly. During commissioning, if the LED indictors on the display panel of the inverter or the battery pack show red, please refer to chapter troubleshooting. 1.5.3.1 Switch on all of the Breakers.
  • Page 17 Commission Report 2. Commission Report Basic Information System name SN number Commissioning date User name Installation address Contact Email Grid codes System checklist √/× Category Model Serial number Quantity Inverter Battery Meter CT Connectors(PV, Grid, Backup, Battery) Inverter Brackets Battery Brackets WIFI module Battery Cables (Power and communi-...
  • Page 18 3. Please read the operation manual carefully before using the system to under- stand the way of safe operation; 4. If the system fails, please contact the AlphaESS service in time, we will deal with the problem as soon as possible End user signature:...

This manual is also suitable for:

Smile-g3-s5Smile-g3-b5