3.2 Fluoro UPS Option

The heat produced by the UPS is transferred to the environment by its ventilation. Cooling air
enters the cabinets through the air inlet (grids) located at the bottom and exhausted through the
outlet on the roof. A suitable ventilation or cooling system must be installed to extract the heat
from the UPS room.
If the UPS is placed on a raised floor, the airflow for UPS cooling should enter from underneath
the UPS, through the appropriate aperture on the raised floor.
If the UPS runs in a dusty environment, we recommend strongly to install filters on the air inlet
of the UPS room. In this case it should be considered that these filters can cause reduced
speed at the air inlet.
The size of the air inlet has therefore to be dimensioned accordingly.
Contact your Local Distributor or one of the Service Centre, which will help you to find valuable
solutions.
The tables below indicate the heat dissipation at full load at PF = 0.8 lag. and charged battery,
up to 1000 m (3280 ft) altitude, for cooling air 25°C (77°F) to 30°C (86°F).
VFI (Voltage Frequency Independent) UPS system where the load is continuously supplied
by the inverter through the rectifier.
SEM (Super Eco Mode) permitting the maximum energy saving.
Chapter 4 Environmental Requirements
NOTICE
The Fluoro UPS batteries require a cooling system to keep ambient temperature
below 25 ºC (77 ºF).
CAUTION
Make sure there is a ventilation air flow, preferably ensured by natural air flow,
otherwise by enforced ventilation, so that hydrogen concentration is below 1%
(according to Standard IEC 62040-1-2).
NOTICE
Do not put anything on the top of the cabinet.
Optima IGS 320, Optima IGS 330 Pre-Installation Manual
Illustration 4-1:
Direction 5537562-1-1EN, Revision 3
159

Advertisement

Table of Contents
loading

This manual is also suitable for:

Optima igs 330

Table of Contents