GE Optima IGS 320 Preinstallation Manual page 26

Table of Contents

Advertisement

Floor is clean and prepared for final floor
covering. Customer has verified floor lev‐
eling meets the equipment installation
6
drawings and PIM specs and no visible
defects are observed. Gantry and table
baseplate are installed prior to delivery (if
applicable)
Access to a working phone at the facility
7
for emergency use, including MR magnet
delivery.
All walls primed (final coat not needed on
Day 1), and counter tops that will support
8
equipment must be installed. No dust-
producing cabinetry work in installation
areas.
Mechanical supplier has been provided
with a set of equipment installation draw‐
9
ings for reference. For California, permit‐
ted construction drawings or PMI-speci‐
fied installation drawings are required.
Conduit/electrical cable ducting/dividers/
access flooring installed, with the excep‐
tion of surface-mounted floor ducting.
10
Wiring to the main disconnect panel is in‐
stalled and compliant with equipment in‐
stallation drawings or pre-installation
manual.
Issued Date: 7/9/07 Rev 11
26
Optima IGS 320, Optima IGS 330 Pre-Installation Manual
X
X
X
X
X
X
X
X
X
GEHC Only: COE # (888) 799.7266 Option 5 (PMI Support)
Direction 5537562-1-1EN, Revision 3
X
X
2 Customer Responsibilities

Advertisement

Table of Contents
loading

This manual is also suitable for:

Optima igs 330

Table of Contents