INSTALLATION
Type B Knockdown: Bolted Construction, Shipped as Parts
Major components/subsystems are removed and shipped on separate skids for a partially-assembled unit.
Figure 7: Partial Disassembly - Representative Illustration
Scope:
• All associated piping and wiring remain attached, if possible
• Compressors and vessels receive an inert gas holding
charge
• All free piping ends are capped
• Suction and discharge lines have bolt-on flanges and, if
possible, remain attached
• Unit ships with vessel and/or head insulation, if ordered
IOM 1297
• Refrigerant will not be shipped with the chiller and must be
procured locally
• Site re-assembly must be supervised or completed by
Daikin Applied service personnel
• Ideal for retrofit applications where installation access is
narrow or restricted and where refrigerant may be secured
locally
11