SECTION 2: INSTALLATION

2.3.2 Anchoring the Unit

If anchoring the unit, see below for anchor locations.
All holes are flush with the bottom surface of the frame.
All dimensions shown are in inches [millimeters]

2.3.3 Housekeeping Pad Requirements

To ensure proper drainage the unit must be installed on a level concrete "housekeeping" pad, with the
condensate assembly supported separately away from the pad, as shown below.
The minimum pad thickness without a Condensate Neutralizer tank is 4 inches (10.2 cm)
AERCO Condensate Neutralizer Tank (P/N 89030), you must ensure enough height for the condensate to
drain into the condensate trap, then into the neutralizer tank, and then to the drain. This may require
that a 1" pit be dug for the Neutralizer Tank. For more information on the Condensate Neutralizer
Tank, see Technical Instructions TID-0074.
NOTE: In all cases a 6" pad eliminates the need for a pit.
Figure 2-3: Condensate Neutralizer Tank Installation
1
Minimum pad height without pit: 5"
Figure 2-2: CFR 3000 Anchor Bolt Locations
1
. If using an